TimeLine Details
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
Proposal received date at each stage of flow.
A.
General Details
(i). Proposal No. :
FP/UK/ROAD/46712/2020
(ii). Name of Project for which Forest Land is required :
C/o Sall Bhatkote to Sukna Salyudi Motor Road
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
Proposed road start from Salla bhatkote to Sukna Salyudi Motor Road. It will connect villages Sukna (population 112) and Salyudi (population 269). Thus it will benefit 382 total population of 2 villages. It will improve economic conditions of connecting villagers.
(iv). File no. :
8B/UCP/06/123/2020/FC
(v). State :
Uttarakhand
(vi). Category of the Project :
Road
(vii). Shape of forest land proposed to be diverted :
Linear
(viii). Area of forest land proposed for diversion(in ha.):
3.78
B.
Time Line
Proposal No.
Submitted by User Agency
Query for Shortcoming(if any) by Nodal Officer
Resubmission of Proposal by User Agency
Query by Nodal Officer for submitting Hard Copies
Uploading(by U.A.) of copies of receipt received from DFO & DC
Division
Circle
Nodal Office
State Government
Regional Office
Stage-I Approval on
Stage-II Approval on
FP/UK/ROAD/46712/2020
25/06/2020
01/07/2020
29/06/2020
08/07/2020
30/06/2020
16/07/2020
13/08/2020
Civil Soyam,Almora
:
13/08/2020
North Kumaun
:
14/09/2020 (
Civil Soyam,Almora
)
Uttarakhand
:
16/09/2020
Uttarakhand
:
20/09/2020
Dehradun
:
30/09/2020
16/10/2020
By :Regional Office
C. Essential Details Sought History
 
Communication between Regional Office & State Government
Communication between State Government & Nodal Officer
Communication between Nodal Officer & Circle
Communication between Circle & Division
Communication between Division & User Agency
Query raised by Circle (North Kumaun) on:
14/09/2020
Replied by DFO (Civil Soyam,Almora) on:
14/09/2020
NOTE:-
Proposal is pending at
Pending With-SG for verifying Compliance of Conditions
.
Close(X)
Close(X)
Please wait ...
EDS History
×
EDS History
×
Proposal No.-
Sno.
From
Status
To
EDS Date
EDS sought/Replied
EDS Letter
1
CF (North Kumaun)
EDS
DFO (Civil Soyam,Almora)
14/09/2020
send back
2
DFO (Civil Soyam,Almora)
REPLY
CF (North Kumaun)
14/09/2020
correction dated 14-09-2020.
EDS History(Stage-II)
×