TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UK/ROAD/45289/2020              (ii). Name of Project for which Forest Land is required : Construction of Kimtoli to Kot Motor Road Under PMGSY Champawat              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The Proposal has been made for construction of Kimtoli to Kot Motor Road under PMGSY, Champawat, which shall provide connectivity to village Kot (274) thus total population 274 serverd with this road.              (iv). File no. : 8B/UCP/06/74/2020/FC              (v). State : Uttarakhand              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 1.995
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/UK/ROAD/45289/202024/04/2020aa02/05/2020   06/05/2020 Champawat :06/05/2020North Kumaun:
  14/05/2020 (Champawat)

Uttarakhand:
26/05/2020
Uttarakhand:
18/06/2020
Dehradun:
15/07/2020
24/07/2020
By :Regional Office
Uttarakhand
18/07/2023
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Nodal Officer (Uttarakhand) on:26/05/2020  
Replied by Circle(North Kumaun) on:16/06/2020  
Query raised by Circle (North Kumaun) on:16/05/2020  
Replied by DFO (Champawat) on:16/05/2020  
Query raised by Circle (North Kumaun) on:20/05/2020  
Replied by DFO (Champawat) on:21/05/2020  
Query raised by Circle (North Kumaun) on:28/05/2020  
Replied by DFO (Champawat) on:30/05/2020  
Query raised by Circle (North Kumaun) on:30/05/2020  
Replied by DFO (Champawat) on:30/05/2020  
Query raised by Circle (North Kumaun) on:01/06/2020  
Replied by DFO (Champawat) on:01/06/2020  
Query raised by Circle (North Kumaun) on:02/06/2020  
Replied by DFO (Champawat) on:06/06/2020  
Query raised by Circle (North Kumaun) on:09/06/2020  
Replied by DFO (Champawat) on:12/06/2020  
Query raised by DFO (Champawat) on:12/05/2020  
Replied by UA on :12/05/2020  
Query raised by DFO (Champawat) on:29/05/2020  
Replied by UA on :30/05/2020  
Query raised by DFO (Champawat) on:02/06/2020  
Replied by UA on :04/06/2020  
Query raised by DFO (Champawat) on:09/06/2020  
Replied by UA on :09/06/2020  
Query raised by DFO (Champawat) on:10/06/2020  
Replied by UA on :10/06/2020  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by Regional Office (Dehradun) on:27/07/2023  
Replied by State Government(Uttarakhand) on:06/02/2024  
Query raised by Regional Office (Dehradun) on:08/07/2024  
Query raised by State Government (Uttarakhand) on:05/08/2023  
Replied by Nodal Officer (Uttarakhand) on:06/02/2024  
Query raised by State Government (Uttarakhand) on:01/08/2024  
Query raised by Nodal Officer on:05/08/2023  
Replied by UA on :13/10/2023  
Query raised by Nodal Officer on:27/10/2023  
Replied by UA on :03/11/2023  
Query raised by Nodal Officer on:25/11/2023  
Replied by UA on :04/12/2023  
Query raised by Nodal Officer on:06/08/2024  
Replied by UA on :29/08/2024  
Query raised by Nodal Officer on:10/09/2024  
Replied by UA on :13/12/2024  
NOTE:- Proposal is pending at Nodal Officer after receiving Compliance of Conditions due to EDS raised by RO for Stage-II .