Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
CF (North Kumaun)
|
EDS
|
DFO (Almora)
|
08/12/2020
|
as per letter no 2298/12-1 dated 08-12-2020
|
|
2
|
DFO (Almora)
|
EDS
|
User Agency (eecdnainitalpwd@rediffmail.com)
|
02/01/2021
|
please submit the hard copy of proposal in CF office
|
|
3
|
User Agency (eecdnainitalpwd@rediffmail.com)
|
REPLY
|
DFO (Almora)
|
12/01/2021
|
The correction have been made as per the instruction received
|
|
4
|
DFO (Almora)
|
REPLY
|
CF (North Kumaun)
|
14/01/2021
|
hard of of the proposal has been already submitted in your office. for reference letter attached by UA in part I
|
|
5
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
29/01/2021
|
The hard copy of the proposal containing original documents is not yet received in this office. The user agency may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part iii as in online web portal.
|
|
6
|
CF (North Kumaun)
|
EDS
|
DFO (Almora)
|
08/02/2021
|
The hard copy of the proposal containing original documents is not yet received in this office. The user agency may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part iii as in online web portal.
|
|
7
|
DFO (Almora)
|
REPLY
|
CF (North Kumaun)
|
19/02/2021
|
Hard copy the proposal has been submitted by as per letter attached
|
|
8
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
25/02/2021
|
Hard copy the proposal has been submitted by as per letter attached
|
|
9
|
Regional Office
|
EDS
|
State secretary
|
31/03/2021
|
The state govt. may attend the following shortcomings as per the attachment here
|
|
10
|
State secretary
|
EDS
|
Nodal Officer
|
08/04/2021
|
State Government may attend to the shortcomings mentioned in the attached document.
|
|
11
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
08/04/2021
|
State Government may attend to the shortcomings mentioned in the attached document.
|
|
12
|
CF (North Kumaun)
|
EDS
|
DFO (Almora)
|
12/04/2021
|
State Government may attend to the shortcomings mentioned in the attached document.
|
|
13
|
DFO (Almora)
|
EDS
|
User Agency (eecdnainitalpwd@rediffmail.com)
|
30/04/2021
|
Do needful as per letter attached
|
|
14
|
User Agency (eecdnainitalpwd@rediffmail.com)
|
REPLY
|
DFO (Almora)
|
09/07/2021
|
The correction have been made as per the instruction received
|
|
15
|
DFO (Almora)
|
EDS
|
User Agency (eecdnainitalpwd@rediffmail.com)
|
04/09/2021
|
please submit the hard copy of EDS reply letter with all attachment in 4 copies
|
|
16
|
User Agency (eecdnainitalpwd@rediffmail.com)
|
REPLY
|
DFO (Almora)
|
12/04/2022
|
The correction have been made as per the instruction received
|
|
17
|
DFO (Almora)
|
EDS
|
User Agency (eecdnainitalpwd@rediffmail.com)
|
28/05/2022
|
Please send the 4 hard copy of the EDS reply letter
|
|
18
|
User Agency (eecdnainitalpwd@rediffmail.com)
|
REPLY
|
DFO (Almora)
|
08/06/2022
|
The correction have been made as per the instruction received
|
|
19
|
DFO (Almora)
|
EDS
|
User Agency (eecdnainitalpwd@rediffmail.com)
|
27/01/2023
|
Please do needful as per letter attached.
|
|
20
|
User Agency (eecdnainitalpwd@rediffmail.com)
|
REPLY
|
DFO (Almora)
|
08/05/2023
|
The correction have been made as per the instruction received
|
|
21
|
DFO (Almora)
|
EDS
|
User Agency (eecdnainitalpwd@rediffmail.com)
|
29/05/2023
|
Please find the letter attached,
|
|
22
|
User Agency (eecdnainitalpwd@rediffmail.com)
|
REPLY
|
DFO (Almora)
|
26/12/2023
|
The correction have been made as per the instruction received
|
|
23
|
DFO (Almora)
|
EDS
|
User Agency (eecdnainitalpwd@rediffmail.com)
|
15/01/2024
|
please submit hard copy of EDS reply letter with appropriate enclosure.
|
|
24
|
User Agency (eecdnainitalpwd@rediffmail.com)
|
REPLY
|
DFO (Almora)
|
26/04/2024
|
The correction have been made as per the instruction received
|
|
25
|
DFO (Almora)
|
EDS
|
User Agency (eecdnainitalpwd@rediffmail.com)
|
09/05/2024
|
Please find the letter attached and do needful.
|
|
26
|
User Agency (eecdnainitalpwd@rediffmail.com)
|
REPLY
|
DFO (Almora)
|
17/05/2024
|
The correction have been made as per the instruction received
|
|
27
|
DFO (Almora)
|
REPLY
|
CF (North Kumaun)
|
15/07/2024
|
the correction have been made as per the instruction received.
|
|
28
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
22/07/2024
|
As per letter no 196/12-1 dated 15-07-2024
|
|
29
|
Nodal Officer
|
REPLY
|
State secretary
|
12/08/2024
|
As per Nodal office letter dated 8-8-2024
|
|
30
|
State secretary
|
REPLY
|
Regional Office
|
23/08/2024
|
EDS reply by nodal office
|
|