Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
18/11/2019
|
The hard copy of the proposal containing original documents is not yet received in this office. The user agency may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part iii as in online web portal.
|
|
2
|
CF (North Kumaun)
|
EDS
|
DFO (Pithoragarh)
|
21/11/2019
|
The hard copy of the proposal containing original documents is not yet received in this office. The user agency may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part iii as in online web portal.
|
|
3
|
DFO (Pithoragarh)
|
EDS
|
User Agency (harishbathyal99@gmail.com)
|
23/11/2019
|
The user agency may provide original hard copy of the proposal to CF office including authenticated copy of Part I to Part iii as in online web portal.
|
|
4
|
User Agency (harishbathyal99@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
28/11/2019
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Pithoragarh)
|
EDS
|
User Agency (harishbathyal99@gmail.com)
|
28/11/2019
|
The user agency may provide original hard copy of the proposal to CF office including authenticated copy of Part I to Part iii as in online web portal. And send receiving letter.
|
|
6
|
User Agency (harishbathyal99@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
29/11/2019
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Pithoragarh)
|
REPLY
|
CF (North Kumaun)
|
29/11/2019
|
hard copy has been sent by user agency.
|
|
8
|
CF (North Kumaun)
|
EDS
|
DFO (Pithoragarh)
|
10/12/2019
|
The hard copy of the proposal containing original documents is not yet received in this office. The user agency may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part iii as in online web portal.
|
|
9
|
DFO (Pithoragarh)
|
REPLY
|
CF (North Kumaun)
|
16/12/2019
|
The correction have been made as per the instruction received
|
|
10
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
19/12/2019
|
hard copy has been sent by user agency.
|
|
11
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
28/12/2019
|
find the letter attached
|
|
12
|
CF (North Kumaun)
|
EDS
|
DFO (Pithoragarh)
|
31/12/2019
|
find the letter attached
|
|
13
|
DFO (Pithoragarh)
|
EDS
|
User Agency (harishbathyal99@gmail.com)
|
03/01/2020
|
find the letter attached
|
|
14
|
User Agency (harishbathyal99@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
06/01/2020
|
The correction have been made as per the instruction received
|
|
15
|
DFO (Pithoragarh)
|
EDS
|
User Agency (harishbathyal99@gmail.com)
|
06/01/2020
|
send reciving
|
|
16
|
User Agency (harishbathyal99@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
14/01/2020
|
The correction have been made as per the instruction received
|
|
17
|
DFO (Pithoragarh)
|
REPLY
|
CF (North Kumaun)
|
14/01/2020
|
point wise obj removed as per nodal off direction.
|
|
18
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
18/01/2020
|
The On line objections raised by Reg. Office /Nodal officer on date 28-12-2019 has been clarified by Dfo Pithoragarh letter no 2590/12-1 dated 14-01-2020
|
|
19
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
04/02/2020
|
find the letter attached
|
|
20
|
CF (North Kumaun)
|
EDS
|
DFO (Pithoragarh)
|
10/02/2020
|
find the letter attached
|
|
21
|
DFO (Pithoragarh)
|
EDS
|
User Agency (harishbathyal99@gmail.com)
|
11/02/2020
|
find the letter attached
|
|
22
|
User Agency (harishbathyal99@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
22/02/2020
|
The correction have been made as per the instruction received
|
|
23
|
DFO (Pithoragarh)
|
REPLY
|
CF (North Kumaun)
|
22/02/2020
|
RESERVE FOREST NOT AFFECTED.SIR RELATED TO CF OFFICE . PLZ CHECK
|
|
24
|
CF (North Kumaun)
|
EDS
|
DFO (Pithoragarh)
|
30/05/2020
|
find the letter attached
|
|
25
|
DFO (Pithoragarh)
|
EDS
|
User Agency (harishbathyal99@gmail.com)
|
02/06/2020
|
find the letter attached
|
|
26
|
User Agency (harishbathyal99@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
21/07/2020
|
The correction have been made as per the instruction received
|
|
27
|
DFO (Pithoragarh)
|
REPLY
|
CF (North Kumaun)
|
25/07/2020
|
Objection has been removed as per letter.
|
|
28
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
27/07/2020
|
The On line objections raised by Reg. Office /Nodal officer on date 04-02-2020 has been clarified by Dfo Pithoragarh letter no 349/12-1 dated 25-07-2020.
|
|