  (i). Proposal No. : FP/UK/ROAD/39349/2019              (ii). Name of Project for which Forest Land is required : Diversion of forest land for widening and strengthening of existing road from Km 399.000 to Km 460.000 of NH-07 (Old NH-58) under Badrinath Forest Division in Chamoli District of Uttarakhand.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of forest land for widening and strengthening of existing road from Km 399.000 to Km 460.000 of NH-07 (Old NH-58) under Badrinath Forest Division in Chamoli District of Uttarakhand. Details is given in additional documents.              (iv). File no. : 8B/UCP/06/76/2020/FC              (v). State : Uttarakhand              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 40.8916
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/UK/ROAD/39349/201911/03/2019aa14/03/2019   20/03/2019 Badrinath,Gopeshwar :22/03/2019Garhwal:
  02/12/2019 (Badrinath,Gopeshwar)

Uttarakhand:
30/05/2020
Uttarakhand:
16/07/2020
Dehradun:
17/07/2020
29/07/2020
By :Regional Office
Uttarakhand
18/03/2021
15/01/2025
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Nodal Officer (Uttarakhand) on:02/06/2020  
Replied by Circle(Garhwal) on:16/07/2020  
Query raised by Circle (Garhwal) on:17/01/2020  
Replied by DFO (Badrinath,Gopeshwar) on:29/05/2020  
Query raised by Circle (Garhwal) on:04/06/2020  
Replied by DFO (Badrinath,Gopeshwar) on:16/07/2020  
Query raised by DFO (Badrinath,Gopeshwar) on:09/05/2019  
Replied by UA on :04/10/2019  
Query raised by DFO (Badrinath,Gopeshwar) on:15/10/2019  
Replied by UA on :02/11/2019  
Query raised by DFO (Badrinath,Gopeshwar) on:17/01/2020  
Replied by UA on :20/02/2020  
Query raised by DFO (Badrinath,Gopeshwar) on:11/03/2020  
Replied by UA on :28/05/2020  
Query raised by DFO (Badrinath,Gopeshwar) on:04/06/2020  
Replied by UA on :28/06/2020  
Query raised by DFO (Badrinath,Gopeshwar) on:10/07/2020  
Replied by UA on :16/07/2020  
Query raised by DFO (Badrinath,Gopeshwar) on:16/07/2020  
Replied by UA on :16/07/2020  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by Regional Office (Dehradun) on:31/03/2021  
Replied by State Government(Uttarakhand) on:20/12/2022  
Query raised by Regional Office (Dehradun) on:17/01/2023  
Replied by State Government(Uttarakhand) on:15/02/2023  
Query raised by Regional Office (Dehradun) on:01/03/2023  
Replied by State Government(Uttarakhand) on:25/11/2023  
Query raised by Regional Office (Dehradun) on:12/01/2024  
Replied by State Government(Uttarakhand) on:23/12/2024  
Query raised by State Government (Uttarakhand) on:15/04/2021  
Replied by Nodal Officer (Uttarakhand) on:20/12/2022  
Query raised by State Government (Uttarakhand) on:25/01/2023  
Replied by Nodal Officer (Uttarakhand) on:15/02/2023  
Query raised by State Government (Uttarakhand) on:15/03/2023  
Replied by Nodal Officer (Uttarakhand) on:25/11/2023  
Query raised by State Government (Uttarakhand) on:27/01/2024  
Replied by Nodal Officer (Uttarakhand) on:18/12/2024  
Query raised by Nodal Officer on:15/04/2021  
Replied by UA on :22/09/2021  
Query raised by Nodal Officer on:30/09/2021  
Replied by UA on :07/12/2021  
Query raised by Nodal Officer on:15/12/2021  
Replied by UA on :19/12/2022  
Query raised by Nodal Officer on:25/01/2023  
Replied by UA on :05/02/2023  
Query raised by Nodal Officer on:10/02/2023  
Replied by UA on :14/02/2023  
Query raised by Nodal Officer on:15/03/2023  
Replied by UA on :01/05/2023  
Query raised by Nodal Officer on:12/05/2023  
Replied by UA on :10/10/2023  
Query raised by Nodal Officer on:27/10/2023  
Replied by UA on :22/11/2023  
Query raised by Nodal Officer on:27/01/2024  
Replied by UA on :18/12/2024  
NOTE:- Stage-II Approval accorded by : Regional Office .