TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UK/ROAD/38909/2019              (ii). Name of Project for which Forest Land is required : Maletha Gwartola to Semwal Gawn Motor road              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The proposed road for connectivity of Unconnected village Semwal Gaon by the length of 1.500 km. and the total population of Benefit villages are 21              (iv). File no. : 8B/UCP/06/33/2020/FC              (v). State : Uttarakhand              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.2795
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/UK/ROAD/38909/201925/02/201909/07/2019  31/05/2019  12/03/2019   24/07/2019  27/06/2019  24/05/2019   28/08/2019   22/10/2019 Narendranagar,Munikireti :07/11/2019Bhagirathi:
  23/12/2019 (Narendranagar,Munikireti)

Uttarakhand:
06/01/2020
Uttarakhand:
20/01/2020
Dehradun:
25/02/2020
13/03/2020
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Nodal Officer (Uttarakhand) on:07/01/2020  
Replied by Circle(Bhagirathi) on:10/01/2020  
Query raised by DFO (Narendranagar,Munikireti) on:19/11/2019  
Replied by UA on :05/12/2019  
NOTE:- Stage-I Approval accorded by : Regional Office .