TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UK/ROAD/38787/2019              (ii). Name of Project for which Forest Land is required : Chelchina Basantpur Jaiti Motor Road Length 10.00Km              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Constuction of Chelchina Basantpur Jaiti Motor Road in Jageshwer constituency Distt Almora. is proposed as a existing Chaja Fatkwaldugra Motor Road. The sanction length of proposed motor road is 10.00 km. The benefited village of this Road are Tyunara, Rosila, Badiyarrait, Tikar, Ranak, Nayasangro              (iv). State : Uttarakhand              (v). Category of the Project : Road              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 2.602
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/UK/ROAD/38787/201925/02/201903/09/2019  12/03/2019   23/01/2020  18/07/2019   24/01/2020   31/01/2020 Civil Soyam,Almora :05/02/2020North Kumaun:
  21/09/2021 (Civil Soyam,Almora)

Uttarakhand:
01/12/2021
Uttarakhand:
18/12/2021
Dehradun:
03/01/2022
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Dehradun) on:12/01/2022  
Replied by State Government(Uttarakhand) on:06/12/2022  
Query raised by Regional Office (Dehradun) on:22/12/2022  
Replied by State Government(Uttarakhand) on:02/04/2024  
Query raised by Regional Office (Dehradun) on:09/08/2024  
Query raised by State Government (Uttarakhand) on:13/01/2022  
Replied by Nodal Officer (Uttarakhand) on:06/12/2022  
Query raised by State Government (Uttarakhand) on:23/12/2022  
Replied by Nodal Officer (Uttarakhand) on:02/04/2024  
Query raised by State Government (Uttarakhand) on:13/08/2024  
Query raised by Nodal Officer (Uttarakhand) on:03/12/2021  
Replied by Circle(North Kumaun) on:09/12/2021  
Query raised by Nodal Officer (Uttarakhand) on:13/01/2022  
Replied by Circle(North Kumaun) on:25/11/2022  
Query raised by Nodal Officer (Uttarakhand) on:23/12/2022  
Replied by Circle(North Kumaun) on:22/08/2023  
Query raised by Nodal Officer (Uttarakhand) on:05/09/2023  
Replied by Circle(North Kumaun) on:30/10/2023  
Query raised by Nodal Officer (Uttarakhand) on:18/11/2023  
Replied by Circle(North Kumaun) on:08/01/2024  
Query raised by Nodal Officer (Uttarakhand) on:25/01/2024  
Replied by Circle(North Kumaun) on:07/03/2024  
Query raised by Nodal Officer (Uttarakhand) on:21/08/2024  
Replied by Circle() on:  
Query raised by Circle (North Kumaun) on:24/09/2021  
Replied by DFO (Civil Soyam,Almora) on:23/11/2021  
Query raised by Circle (North Kumaun) on:18/01/2022  
Replied by DFO (Civil Soyam,Almora) on:20/10/2022  
Query raised by Circle (North Kumaun) on:28/12/2022  
Replied by DFO (Civil Soyam,Almora) on:21/07/2023  
Query raised by Circle (North Kumaun) on:31/07/2023  
Replied by DFO (Civil Soyam,Almora) on:04/08/2023  
Query raised by Circle (North Kumaun) on:22/09/2023  
Replied by DFO (Civil Soyam,Almora) on:05/10/2023  
Query raised by Circle (North Kumaun) on:02/12/2023  
Replied by DFO (Civil Soyam,Almora) on:28/12/2023  
Query raised by Circle (North Kumaun) on:29/01/2024  
Replied by DFO (Civil Soyam,Almora) on:02/03/2024  
Query raised by Circle (North Kumaun) on:21/08/2024  
Replied by DFO (Civil Soyam,Almora) on:03/01/2025  
Query raised by Circle (North Kumaun) on:03/01/2025  
Replied by DFO () on:  
Query raised by DFO (Civil Soyam,Almora) on:25/02/2020  
Replied by UA on :31/07/2021  
Query raised by DFO (Civil Soyam,Almora) on:07/09/2021  
Replied by UA on :15/09/2021  
Query raised by DFO (Civil Soyam,Almora) on:28/09/2021  
Replied by UA on :25/10/2021  
Query raised by DFO (Civil Soyam,Almora) on:28/01/2022  
Replied by UA on :23/09/2022  
Query raised by DFO (Civil Soyam,Almora) on:28/12/2022  
Replied by UA on :07/01/2023  
Query raised by DFO (Civil Soyam,Almora) on:11/01/2023  
Replied by UA on :11/04/2023  
Query raised by DFO (Civil Soyam,Almora) on:08/06/2023  
Replied by UA on :03/07/2023  
Query raised by DFO (Civil Soyam,Almora) on:24/08/2024  
Replied by UA on :21/12/2024  
NOTE:- Proposal is pending at DFO due to EDS raised by Regional Office .