Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Ramnagar)
|
EDS
|
User Agency (eecdrmr@rediffmail.com)
|
19/11/2019
|
Find the attachment and do the needful.
|
|
2
|
User Agency (eecdrmr@rediffmail.com)
|
REPLY
|
DFO (Ramnagar)
|
03/09/2020
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Ramnagar)
|
EDS
|
User Agency (eecdrmr@rediffmail.com)
|
15/09/2020
|
Find the attachment and do the needful
|
|
4
|
User Agency (eecdrmr@rediffmail.com)
|
REPLY
|
DFO (Ramnagar)
|
22/10/2020
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Ramnagar)
|
EDS
|
User Agency (eecdrmr@rediffmail.com)
|
26/10/2020
|
the distance certificate is not attached with the proposal only the distance map is attached. User agency may attached the distance certificate and do the needful.
|
|
6
|
User Agency (eecdrmr@rediffmail.com)
|
REPLY
|
DFO (Ramnagar)
|
24/12/2020
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Ramnagar)
|
EDS
|
User Agency (eecdrmr@rediffmail.com)
|
31/12/2020
|
User Agency may submit the hard copy of the arial distance certificate in 05 copies.
|
|
8
|
User Agency (eecdrmr@rediffmail.com)
|
REPLY
|
DFO (Ramnagar)
|
02/01/2021
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Ramnagar)
|
EDS
|
User Agency (eecdrmr@rediffmail.com)
|
10/08/2023
|
please submit the corrections in hard copy
|
|