TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UK/ROAD/36098/2018              (ii). Name of Project for which Forest Land is required : Construction OF Soughar Pantgoun Chamarkhan Sageena Motor Road              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : This road joining the village Sageena in almora distt at uttrakhand The New construction work (I phase) was sanctioned for Soughar pantgoun chamarkhan sageena nougoun lachhamola motor road under Ranikhet Assembly area in Almora District. Total lengh is 3 km. Benifated villages sageena. are sat              (iv). File no. : 8B/UCP/06/163/2020/FC              (v). State : Uttarakhand              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.225
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/UK/ROAD/36098/201805/10/201807/08/2019  20/07/2019  17/06/2019  21/05/2019  09/04/2019  26/02/2019  07/02/2019  29/12/2018  01/12/2018  11/10/2018   28/08/2019  30/07/2019  29/06/2019  14/06/2019  01/05/2019  04/04/2019  20/02/2019  17/01/2019  10/12/2018  27/11/2018   30/08/2019   28/09/2019 Almora :25/10/2019North Kumaun:
  01/01/2020 (Almora)

Uttarakhand:
15/01/2020
Uttarakhand:
23/09/2020
Dehradun:
15/12/2020
23/09/2021
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Dehradun) on:30/12/2020  
Replied by State Government(Uttarakhand) on:17/09/2021  
Query raised by State Government (Uttarakhand) on:01/01/2021  
Replied by Nodal Officer (Uttarakhand) on:17/09/2021  
Query raised by Nodal Officer (Uttarakhand) on:16/01/2020  
Replied by Circle(North Kumaun) on:09/06/2020  
Query raised by Nodal Officer (Uttarakhand) on:12/06/2020  
Replied by Circle(North Kumaun) on:29/08/2020  
Query raised by Nodal Officer (Uttarakhand) on:02/01/2021  
Replied by Circle(North Kumaun) on:08/01/2021  
Query raised by Nodal Officer (Uttarakhand) on:09/01/2021  
Replied by Circle(North Kumaun) on:14/09/2021  
Query raised by Circle (North Kumaun) on:18/01/2020  
Replied by DFO (Almora) on:05/06/2020  
Query raised by Circle (North Kumaun) on:01/07/2020  
Replied by DFO (Almora) on:26/08/2020  
Query raised by Circle (North Kumaun) on:04/01/2021  
Replied by DFO (Almora) on:05/01/2021  
Query raised by Circle (North Kumaun) on:12/01/2021  
Replied by DFO (Almora) on:10/08/2021  
Query raised by Circle (North Kumaun) on:11/08/2021  
Replied by DFO (Almora) on:02/09/2021  
Query raised by DFO (Almora) on:24/01/2020  
Replied by UA on :28/01/2020  
Query raised by DFO (Almora) on:20/03/2020  
Replied by UA on :27/05/2020  
Query raised by DFO (Almora) on:14/01/2021  
Replied by UA on :05/02/2021  
Query raised by DFO (Almora) on:17/03/2021  
Replied by UA on :23/03/2021  
Query raised by DFO (Almora) on:27/03/2021  
Replied by UA on :03/04/2021  
Query raised by DFO (Almora) on:06/04/2021  
Replied by UA on :09/04/2021  
Query raised by DFO (Almora) on:04/06/2021  
Replied by UA on :28/06/2021  
Query raised by DFO (Almora) on:24/07/2021  
Replied by UA on :29/07/2021  
NOTE:- Stage-I Approval accorded by : Regional Office .