Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
12/07/2021
|
find the letter attached
|
|
2
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
23/07/2021
|
As per letter no 274/12-1 dated 23-07-2021
|
|
3
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
29/07/2021
|
find the letter attached
|
|
4
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
28/04/2022
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
27/05/2022
|
find the letter attached..
|
|
6
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
28/06/2022
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
29/06/2022
|
plz find enclosed.
|
|
8
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
02/07/2022
|
As per letter no 5830/12-1 dated 30-06-2022
|
|
9
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
12/07/2022
|
find the letter attached
|
|
10
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
14/07/2022
|
find the letter attached
|
|
11
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
14/07/2022
|
find the letter attached
|
|
12
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
21/10/2023
|
The correction have been made as per the instruction received
|
|
13
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
09/11/2023
|
plzfind enclosed
|
|
14
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
18/11/2023
|
Send back
|
|
15
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
18/11/2023
|
plz find enclosed.
|
|
16
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
30/11/2023
|
As per letter no 1284/12-1 dated 17-11-2023
|
|
17
|
State secretary
|
EDS
|
Nodal Officer
|
04/07/2024
|
On the observation of proposal it has been found that area mentioned in hard copy of forwarding letter is 2.441 ha. whereas in the letter of recommendation uploaded online the area mentioned is 2.413 ha. Hence, Nodal office kindly provide the forwarding letter in hard copy with required rectification.
|
|
18
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
09/07/2024
|
As per State Government EDS
|
|
19
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
09/07/2024
|
plz encloser attached
|
|
20
|
Nodal Officer
|
REPLY
|
State secretary
|
07/09/2024
|
PFA
|
|
21
|
State secretary
|
EDS
|
Nodal Officer
|
07/11/2024
|
Kindly justify as per attachment
|
|