Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
CF (Bhagirathi)
|
EDS
|
DFO (Uttarkashi)
|
22/03/2018
|
Hard Copy of this Proposal does not received yet on this office.
|
|
2
|
DFO (Uttarkashi)
|
EDS
|
User Agency (eepwdbhatwari@rediffmail.com)
|
30/03/2018
|
Hard Copy of this Proposal does not received yet on this office.
|
|
3
|
User Agency (eepwdbhatwari@rediffmail.com)
|
REPLY
|
DFO (Uttarkashi)
|
07/04/2018
|
The correction have been made as per the instruction received
|
|
4
|
DFO (Uttarkashi)
|
REPLY
|
CF (Bhagirathi)
|
10/04/2018
|
Sir, Objection clear, hard copy submit by UA.
|
|
5
|
DFO (Uttarkashi)
|
REPLY
|
CF (Bhagirathi)
|
10/04/2018
|
Sir, Objection clear, hard copy submit by UA.
|
|
6
|
Nodal Officer
|
EDS
|
CF (Bhagirathi)
|
24/04/2018
|
The hard copy of the proposal containing original documents is not yet received in this office. The user agency may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part iii as in online web portal.
|
|
7
|
CF (Bhagirathi)
|
REPLY
|
Nodal Officer
|
28/04/2018
|
Sir,
Hard Copy Of this Proposal is send to Your Office on dated 28-04-2018
|
|
8
|
Nodal Officer
|
EDS
|
CF (Bhagirathi)
|
08/05/2018
|
4. In the hard copy all documents are photocopies but as per latest instructions, hard copy with original / attested document is required to be furnished which may be done now but important documents like FRA certificate and digital maps of proposed road and area proposed for CA should be in original.
|
|
9
|
CF (Bhagirathi)
|
EDS
|
DFO (Uttarkashi)
|
09/05/2018
|
4. In the hard copy all documents are photocopies but as per latest instructions, hard copy with original / attested document is required to be furnished which may be done now but important documents like FRA certificate and digital maps of proposed road and area proposed for CA should be in original.
|
|
10
|
DFO (Uttarkashi)
|
EDS
|
User Agency (eepwdbhatwari@rediffmail.com)
|
10/05/2018
|
4. In the hard copy all documents are photocopies but as per latest instructions, hard copy with original / attested document is required to be furnished which may be done now but important documents like FRA certificate and digital maps of proposed road and area proposed for CA should be in original.
|
|
11
|
User Agency (eepwdbhatwari@rediffmail.com)
|
REPLY
|
DFO (Uttarkashi)
|
21/06/2018
|
The correction have been made as per the instruction received
|
|
12
|
DFO (Uttarkashi)
|
EDS
|
User Agency (eepwdbhatwari@rediffmail.com)
|
07/07/2018
|
Sir,objection letter not uploaded & hard copy not submitted in this office
|
|
13
|
User Agency (eepwdbhatwari@rediffmail.com)
|
REPLY
|
DFO (Uttarkashi)
|
13/07/2018
|
The correction have been made as per the instruction received
|
|
14
|
DFO (Uttarkashi)
|
EDS
|
User Agency (eepwdbhatwari@rediffmail.com)
|
20/07/2018
|
4. In the hard copy all documents are photocopies but as per latest instructions, hard copy with original / attested document is required to be furnished which may be done now but important documents like FRA certificate and digital maps of proposed road and area proposed for CA should be in original
|
|
15
|
User Agency (eepwdbhatwari@rediffmail.com)
|
REPLY
|
DFO (Uttarkashi)
|
26/07/2018
|
The correction have been made as per the instruction received
|
|
16
|
DFO (Uttarkashi)
|
EDS
|
User Agency (eepwdbhatwari@rediffmail.com)
|
30/07/2018
|
Sir,objection clear as per attachment to pdf file.
|
|
17
|
User Agency (eepwdbhatwari@rediffmail.com)
|
REPLY
|
DFO (Uttarkashi)
|
30/07/2018
|
The correction have been made as per the instruction received
|
|
18
|
DFO (Uttarkashi)
|
REPLY
|
CF (Bhagirathi)
|
30/07/2018
|
Sir,objection clear as per attachment to pdf file
|
|
19
|
CF (Bhagirathi)
|
EDS
|
DFO (Uttarkashi)
|
31/07/2018
|
Sir,
The Shortcoming does not rectified as per instruction. So Plz attend the following objection.
1- In the hard copy all documents are photocopies but as per latest instructions, hard copy with original / attested document is required to be furnished which may be done now but important documents like FRA certificate and digital maps of proposed road and area proposed for CA should be in original.
|
|
20
|
DFO (Uttarkashi)
|
EDS
|
User Agency (eepwdbhatwari@rediffmail.com)
|
31/07/2018
|
Sir, The Shortcoming does not rectified as per instruction. So Plz attend the following objection. 1- In the hard copy all documents are photocopies but as per latest instructions, hard copy with original / attested document is required to be furnished which may be done now but important documents like FRA certificate and digital maps of proposed road and area proposed for CA should be in original.
|
|
21
|
User Agency (eepwdbhatwari@rediffmail.com)
|
REPLY
|
DFO (Uttarkashi)
|
28/08/2018
|
The correction have been made as per the instruction received
|
|
22
|
DFO (Uttarkashi)
|
REPLY
|
CF (Bhagirathi)
|
29/08/2018
|
Sir, objection clear as per attachment to PDF file.
|
|
23
|
CF (Bhagirathi)
|
REPLY
|
Nodal Officer
|
30/08/2018
|
Find the letter attached.
|
|
24
|
Nodal Officer
|
EDS
|
CF (Bhagirathi)
|
01/09/2018
|
find the letter attached
|
|
25
|
CF (Bhagirathi)
|
EDS
|
DFO (Uttarkashi)
|
02/09/2018
|
Find the letter attached.
|
|
26
|
DFO (Uttarkashi)
|
EDS
|
User Agency (eepwdbhatwari@rediffmail.com)
|
05/09/2018
|
Find the letter attached.
|
|
27
|
User Agency (eepwdbhatwari@rediffmail.com)
|
REPLY
|
DFO (Uttarkashi)
|
10/09/2018
|
The correction have been made as per the instruction received
|
|
28
|
DFO (Uttarkashi)
|
EDS
|
User Agency (eepwdbhatwari@rediffmail.com)
|
10/09/2018
|
Find the letter attached.
|
|
29
|
User Agency (eepwdbhatwari@rediffmail.com)
|
REPLY
|
DFO (Uttarkashi)
|
04/04/2019
|
The correction have been made as per the instruction received
|
|
30
|
DFO (Uttarkashi)
|
REPLY
|
CF (Bhagirathi)
|
18/04/2019
|
Sir, objection clear as per attachment to PDF file.
|
|
31
|
CF (Bhagirathi)
|
EDS
|
DFO (Uttarkashi)
|
26/04/2019
|
user agency may attend the shortcomings as per attachment.
|
|
32
|
DFO (Uttarkashi)
|
EDS
|
User Agency (eepwdbhatwari@rediffmail.com)
|
26/04/2019
|
user agency may attend the shortcomings as per attachment.
|
|
33
|
User Agency (eepwdbhatwari@rediffmail.com)
|
REPLY
|
DFO (Uttarkashi)
|
24/05/2019
|
The correction have been made as per the instruction received
|
|
34
|
DFO (Uttarkashi)
|
EDS
|
User Agency (eepwdbhatwari@rediffmail.com)
|
28/05/2019
|
sir, justification certificate still not uploaded at para- D i. other certificate has been uploaded in the place of justification
|
|
35
|
User Agency (eepwdbhatwari@rediffmail.com)
|
REPLY
|
DFO (Uttarkashi)
|
28/05/2019
|
The correction have been made as per the instruction received
|
|
36
|
DFO (Uttarkashi)
|
EDS
|
User Agency (eepwdbhatwari@rediffmail.com)
|
03/06/2019
|
Sir, plz rectify the eds dated 01.09.2018. query no-1,3 & 5 still not rectified by you.
|
|
37
|
User Agency (eepwdbhatwari@rediffmail.com)
|
REPLY
|
DFO (Uttarkashi)
|
11/06/2019
|
The correction have been made as per the instruction received
|
|
38
|
DFO (Uttarkashi)
|
REPLY
|
CF (Bhagirathi)
|
20/06/2019
|
sir objection clear as per attachment to pdf file.
|
|
39
|
CF (Bhagirathi)
|
EDS
|
DFO (Uttarkashi)
|
08/07/2019
|
shortcomings of previous EDS letter still remaining, please find the letter attached herewith.
|
|
40
|
DFO (Uttarkashi)
|
EDS
|
User Agency (eepwdbhatwari@rediffmail.com)
|
08/07/2019
|
shortcomings of previous EDS letter still remaining, please find the letter attached herewith.
|
|
41
|
User Agency (eepwdbhatwari@rediffmail.com)
|
REPLY
|
DFO (Uttarkashi)
|
24/07/2019
|
The correction have been made as per the instruction received
|
|
42
|
DFO (Uttarkashi)
|
EDS
|
User Agency (eepwdbhatwari@rediffmail.com)
|
25/07/2019
|
Find the letter attached
|
|
43
|
User Agency (eepwdbhatwari@rediffmail.com)
|
REPLY
|
DFO (Uttarkashi)
|
25/07/2019
|
The correction have been made as per the instruction received
|
|
44
|
DFO (Uttarkashi)
|
REPLY
|
CF (Bhagirathi)
|
25/07/2019
|
sir objection clear as per attachment to pdf file.
|
|
45
|
CF (Bhagirathi)
|
EDS
|
DFO (Uttarkashi)
|
26/07/2019
|
Point no. 2 and Point no. 3 is still have not been rectified.
|
|
46
|
DFO (Uttarkashi)
|
EDS
|
User Agency (eepwdbhatwari@rediffmail.com)
|
26/07/2019
|
Point no. 2 and Point no. 3 is still have not been rectified.
|
|
47
|
User Agency (eepwdbhatwari@rediffmail.com)
|
REPLY
|
DFO (Uttarkashi)
|
26/07/2019
|
The correction have been made as per the instruction received
|
|
48
|
DFO (Uttarkashi)
|
EDS
|
User Agency (eepwdbhatwari@rediffmail.com)
|
27/07/2019
|
Point no. 2 and Point no. 3 is still have not been rectified.
|
|
49
|
User Agency (eepwdbhatwari@rediffmail.com)
|
REPLY
|
DFO (Uttarkashi)
|
27/07/2019
|
The correction have been made as per the instruction received
|
|
50
|
DFO (Uttarkashi)
|
EDS
|
User Agency (eepwdbhatwari@rediffmail.com)
|
27/07/2019
|
Point no. 2 and Point no. 3 is still have not been rectified.
|
|
51
|
User Agency (eepwdbhatwari@rediffmail.com)
|
REPLY
|
DFO (Uttarkashi)
|
27/07/2019
|
The correction have been made as per the instruction received
|
|
52
|
DFO (Uttarkashi)
|
EDS
|
User Agency (eepwdbhatwari@rediffmail.com)
|
27/07/2019
|
The correction is still have not been rectified.
|
|
53
|
User Agency (eepwdbhatwari@rediffmail.com)
|
REPLY
|
DFO (Uttarkashi)
|
27/07/2019
|
The correction have been made as per the instruction received
|
|
54
|
DFO (Uttarkashi)
|
REPLY
|
CF (Bhagirathi)
|
27/07/2019
|
The correction have been made as per the instruction received
|
|
55
|
CF (Bhagirathi)
|
REPLY
|
Nodal Officer
|
27/07/2019
|
sir, the shortcomings have been resolved as per attached file.
|
|
56
|
Nodal Officer
|
EDS
|
CF (Bhagirathi)
|
31/07/2019
|
find the letter attached
|
|
57
|
CF (Bhagirathi)
|
EDS
|
DFO (Uttarkashi)
|
01/08/2019
|
find the letter attached
|
|
58
|
DFO (Uttarkashi)
|
EDS
|
User Agency (eepwdbhatwari@rediffmail.com)
|
01/08/2019
|
find the letter attached
|
|
59
|
User Agency (eepwdbhatwari@rediffmail.com)
|
REPLY
|
DFO (Uttarkashi)
|
01/11/2019
|
The correction have been made as per the instruction received
|
|
60
|
DFO (Uttarkashi)
|
EDS
|
User Agency (eepwdbhatwari@rediffmail.com)
|
14/11/2019
|
Eds point no 1 still has not been rectified, plz rectify
|
|
61
|
User Agency (eepwdbhatwari@rediffmail.com)
|
REPLY
|
DFO (Uttarkashi)
|
14/11/2019
|
The correction have been made as per the instruction received
|
|
62
|
DFO (Uttarkashi)
|
EDS
|
User Agency (eepwdbhatwari@rediffmail.com)
|
18/11/2019
|
Eds point no 1 still has not been rectified, plz rectify
|
|
63
|
User Agency (eepwdbhatwari@rediffmail.com)
|
REPLY
|
DFO (Uttarkashi)
|
28/11/2019
|
The correction have been made as per the instruction received
|
|
64
|
DFO (Uttarkashi)
|
REPLY
|
CF (Bhagirathi)
|
30/11/2019
|
sir objection clear as per attachment to pdf file.
|
|
65
|
CF (Bhagirathi)
|
EDS
|
DFO (Uttarkashi)
|
20/12/2019
|
The hard copy of EDS reply along with annexure yet not received to this office.
|
|
66
|
DFO (Uttarkashi)
|
EDS
|
User Agency (eepwdbhatwari@rediffmail.com)
|
21/12/2019
|
The hard copy of EDS reply along with annexure yet not received to this office.
|
|
67
|
User Agency (eepwdbhatwari@rediffmail.com)
|
REPLY
|
DFO (Uttarkashi)
|
28/12/2019
|
The correction have been made as per the instruction received
|
|
68
|
DFO (Uttarkashi)
|
REPLY
|
CF (Bhagirathi)
|
15/01/2020
|
Sir objection clear as per attachment to pdf file.
|
|
69
|
CF (Bhagirathi)
|
REPLY
|
Nodal Officer
|
23/01/2020
|
sir, the correction have been made as per instruction received.
|
|
70
|
Regional Office
|
EDS
|
State secretary
|
26/02/2020
|
State Govt. may attend the shortcomings as per the attachment.
|
|
71
|
State secretary
|
EDS
|
Nodal Officer
|
26/02/2020
|
state govt. may attend the following shortcomings as per the attachment here
|
|
72
|
Nodal Officer
|
EDS
|
CF (Bhagirathi)
|
27/02/2020
|
state govt. may attend the following shortcomings as per the attachment here
|
|
73
|
CF (Bhagirathi)
|
EDS
|
DFO (Uttarkashi)
|
02/03/2020
|
attend the following shortcomings as per the attachment here
|
|
74
|
DFO (Uttarkashi)
|
EDS
|
User Agency (eepwdbhatwari@rediffmail.com)
|
05/03/2020
|
attend the following shortcomings as per the attachment here
|
|
75
|
User Agency (eepwdbhatwari@rediffmail.com)
|
REPLY
|
DFO (Uttarkashi)
|
18/07/2020
|
The correction have been made as per the instruction received
|
|
76
|
DFO (Uttarkashi)
|
REPLY
|
CF (Bhagirathi)
|
21/07/2020
|
Sir objection clear as per attachment to pdf file.
|
|
77
|
CF (Bhagirathi)
|
REPLY
|
Nodal Officer
|
30/07/2020
|
EDS Reply done find the letter attached.
|
|
78
|
Nodal Officer
|
EDS
|
CF (Bhagirathi)
|
05/08/2020
|
find the letter attached
|
|
79
|
CF (Bhagirathi)
|
EDS
|
DFO (Uttarkashi)
|
07/08/2020
|
find the letter attached
|
|
80
|
DFO (Uttarkashi)
|
EDS
|
User Agency (eepwdbhatwari@rediffmail.com)
|
07/08/2020
|
find the letter attached
|
|
81
|
User Agency (eepwdbhatwari@rediffmail.com)
|
REPLY
|
DFO (Uttarkashi)
|
20/08/2020
|
The correction have been made as per the instruction received
|
|
82
|
DFO (Uttarkashi)
|
REPLY
|
CF (Bhagirathi)
|
21/08/2020
|
Sir objection clear as per attachment to pdf file.
|
|
83
|
CF (Bhagirathi)
|
REPLY
|
Nodal Officer
|
26/08/2020
|
find the letter Attached.
|
|
84
|
Nodal Officer
|
REPLY
|
State secretary
|
28/08/2020
|
the shortcomings have been resolved as per attached file.
|
|
85
|
State secretary
|
REPLY
|
Regional Office
|
28/08/2020
|
sir, the shortcomings have been resolved as per attached file.
|
|