TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UK/ROAD/23851/2017              (ii). Name of Project for which Forest Land is required : Construction of mustik sour kuroli motor road from kankradi bend to kisanpur manpur motor road              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : After road construction .village kankradi .serpur ,kuroli,bongadi and kisanpur ,manpur connect by road and all village purchege all goods in market.              (iv). File no. : 8B/UCP/06/100/2018/FC              (v). State : Uttarakhand              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 1.163
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/UK/ROAD/23851/201731/01/201711/09/2017  02/09/2017  07/08/2017  26/06/2017  04/06/2017  27/03/2017   11/09/2017  04/09/2017  22/08/2017  01/07/2017  14/06/2017  10/04/2017   13/09/2017   22/09/2017 Uttarkashi :03/10/2017Bhagirathi:
  04/01/2018 (Uttarkashi)

Uttarakhand:
22/02/2018
Uttarakhand:
11/03/2018
Dehradun:
28/03/2018
09/09/2020
By :Regional Office
Uttarakhand
05/04/2023
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Dehradun) on:09/04/2018  
Replied by State Government(Uttarakhand) on:04/09/2018  
Query raised by Regional Office (Dehradun) on:08/10/2018  
Replied by State Government(Uttarakhand) on:26/01/2020  
Query raised by Regional Office (Dehradun) on:07/02/2020  
Replied by State Government(Uttarakhand) on:28/08/2020  
Query raised by State Government (Uttarakhand) on:11/04/2018  
Replied by Nodal Officer (Uttarakhand) on:01/09/2018  
Query raised by State Government (Uttarakhand) on:09/10/2018  
Replied by Nodal Officer (Uttarakhand) on:26/01/2020  
Query raised by State Government (Uttarakhand) on:11/02/2020  
Replied by Nodal Officer (Uttarakhand) on:28/08/2020  
Query raised by Nodal Officer (Uttarakhand) on:23/02/2018  
Replied by Circle(Bhagirathi) on:27/02/2018  
Query raised by Nodal Officer (Uttarakhand) on:13/04/2018  
Replied by Circle(Bhagirathi) on:17/04/2018  
Query raised by Nodal Officer (Uttarakhand) on:08/05/2018  
Replied by Circle(Bhagirathi) on:31/08/2018  
Query raised by Nodal Officer (Uttarakhand) on:09/10/2018  
Replied by Circle(Bhagirathi) on:21/11/2019  
Query raised by Nodal Officer (Uttarakhand) on:25/11/2019  
Replied by Circle(Bhagirathi) on:28/11/2019  
Query raised by Nodal Officer (Uttarakhand) on:04/12/2019  
Replied by Circle(Bhagirathi) on:21/01/2020  
Query raised by Nodal Officer (Uttarakhand) on:14/02/2020  
Replied by Circle(Bhagirathi) on:26/08/2020  
Query raised by Circle (Bhagirathi) on:11/01/2018  
Replied by DFO (Uttarkashi) on:06/02/2018  
Query raised by Circle (Bhagirathi) on:09/05/2018  
Replied by DFO (Uttarkashi) on:29/08/2018  
Query raised by Circle (Bhagirathi) on:10/10/2018  
Replied by DFO (Uttarkashi) on:06/03/2019  
Query raised by Circle (Bhagirathi) on:16/03/2019  
Replied by DFO (Uttarkashi) on:31/05/2019  
Query raised by Circle (Bhagirathi) on:12/06/2019  
Replied by DFO (Uttarkashi) on:24/07/2019  
Query raised by Circle (Bhagirathi) on:03/08/2019  
Replied by DFO (Uttarkashi) on:14/11/2019  
Query raised by Circle (Bhagirathi) on:15/11/2019  
Replied by DFO (Uttarkashi) on:15/11/2019  
Query raised by Circle (Bhagirathi) on:10/12/2019  
Replied by DFO (Uttarkashi) on:15/01/2020  
Query raised by Circle (Bhagirathi) on:17/02/2020  
Replied by DFO (Uttarkashi) on:16/08/2020  
Query raised by DFO (Uttarkashi) on:15/11/2017  
Replied by UA on :22/11/2017  
Query raised by DFO (Uttarkashi) on:11/01/2018  
Replied by UA on :06/02/2018  
Query raised by DFO (Uttarkashi) on:10/05/2018  
Replied by UA on :21/06/2018  
Query raised by DFO (Uttarkashi) on:07/07/2018  
Replied by UA on :13/07/2018  
Query raised by DFO (Uttarkashi) on:20/07/2018  
Replied by UA on :26/07/2018  
Query raised by DFO (Uttarkashi) on:30/07/2018  
Replied by UA on :28/08/2018  
Query raised by DFO (Uttarkashi) on:10/10/2018  
Replied by UA on :21/02/2019  
Query raised by DFO (Uttarkashi) on:27/03/2019  
Replied by UA on :17/05/2019  
Query raised by DFO (Uttarkashi) on:22/05/2019  
Replied by UA on :27/05/2019  
Query raised by DFO (Uttarkashi) on:14/06/2019  
Replied by UA on :05/07/2019  
Query raised by DFO (Uttarkashi) on:10/07/2019  
Replied by UA on :22/07/2019  
Query raised by DFO (Uttarkashi) on:05/08/2019  
Replied by UA on :01/11/2019  
Query raised by DFO (Uttarkashi) on:13/12/2019  
Replied by UA on :28/12/2019  
Query raised by DFO (Uttarkashi) on:20/02/2020  
Replied by UA on :16/03/2020  
Query raised by DFO (Uttarkashi) on:15/05/2020  
Replied by UA on :11/06/2020  
Query raised by DFO (Uttarkashi) on:23/06/2020  
Replied by UA on :07/08/2020  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by Regional Office (Dehradun) on:24/04/2023  
Query raised by State Government (Uttarakhand) on:28/04/2023  
Query raised by Nodal Officer on:19/01/2024  
Replied by UA on :06/06/2024  
Query raised by Nodal Officer on:30/07/2024  
Replied by UA on :01/08/2024  
Query raised by Nodal Officer on:12/08/2024  
Replied by UA on :13/08/2024  
Query raised by Nodal Officer on:22/09/2024  
Replied by UA on :05/11/2024  
NOTE:- Proposal is pending at Nodal Officer after receiving Compliance of Conditions due to EDS raised by RO for Stage-II .
Close(X)
Close(X)