| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
Nodal Officer
|
EDS
|
CF (Bhagirathi)
|
18/03/2017
|
The hard copy of the proposal containing original documents is not yet received in this office. The CF may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part V as in online web portal.
|
|
|
2
|
CF (Bhagirathi)
|
REPLY
|
Nodal Officer
|
23/03/2017
|
Sir,
Proposal hard copy receiving will be attached.
|
|
|
3
|
Nodal Officer
|
EDS
|
CF (Bhagirathi)
|
05/04/2017
|
find the letter attached
|
|
|
4
|
CF (Bhagirathi)
|
EDS
|
DFO (Narendranagar,Munikireti)
|
10/04/2017
|
Find the attachment and clarify objection raised by Nodal Officer.
|
|
|
5
|
DFO (Narendranagar,Munikireti)
|
EDS
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
17/04/2017
|
Find the attachment and clarify objection raised by Nodal Officer.
|
|
|
6
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
REPLY
|
DFO (Narendranagar,Munikireti)
|
22/07/2017
|
The correction have been made as per the instruction received
|
|
|
7
|
DFO (Narendranagar,Munikireti)
|
EDS
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
27/07/2017
|
Please upload FRA in part-1 para k with date.
|
|
|
8
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
REPLY
|
DFO (Narendranagar,Munikireti)
|
31/07/2017
|
The correction have been made as per the instruction received
|
|
|
9
|
DFO (Narendranagar,Munikireti)
|
EDS
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
04/08/2017
|
Please Provide us Complete FRA Certificate and CA Scheme in Original Re wise Document.
|
|
|
10
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
REPLY
|
DFO (Narendranagar,Munikireti)
|
24/08/2017
|
The correction have been made as per the instruction received
|
|
|
11
|
DFO (Narendranagar,Munikireti)
|
EDS
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
30/08/2017
|
Please Provide us Complete FRA Certificate and CA Scheme in Original Re wise Document.
|
|
|
12
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
REPLY
|
DFO (Narendranagar,Munikireti)
|
30/08/2017
|
The correction have been made as per the instruction received
|
|
|
13
|
DFO (Narendranagar,Munikireti)
|
REPLY
|
CF (Bhagirathi)
|
05/09/2017
|
Sir The correction have been made as per the instruction received.
|
|
|
14
|
CF (Bhagirathi)
|
REPLY
|
Nodal Officer
|
06/09/2017
|
Objection clear as per attached PDF file.
|
|
|
15
|
Nodal Officer
|
EDS
|
CF (Bhagirathi)
|
14/09/2017
|
please send the reply as a hard copy also
|
|
|
16
|
CF (Bhagirathi)
|
REPLY
|
Nodal Officer
|
16/09/2017
|
Sir, please attached the file.
|
|
|
17
|
Nodal Officer
|
EDS
|
CF (Bhagirathi)
|
28/09/2017
|
please send the reply as a hard copy also.the reply is yet not recived in this off
|
|
|
18
|
CF (Bhagirathi)
|
REPLY
|
Nodal Officer
|
28/09/2017
|
The hard copy of the proposal is already send to Your Office on dated 13-09-2017
|
|
|
19
|
Regional Office
|
EDS
|
State secretary
|
30/10/2017
|
State Government may attend to the shortcomings mentioned in the attached document.
|
|
|
20
|
State secretary
|
EDS
|
Nodal Officer
|
31/10/2017
|
State Government may attend to the shortcomings mentioned in the attached document.
|
|
|
21
|
Nodal Officer
|
EDS
|
CF (Bhagirathi)
|
01/11/2017
|
State Government may attend to the shortcomings mentioned in the attached document.
|
|
|
22
|
CF (Bhagirathi)
|
EDS
|
DFO (Narendranagar,Munikireti)
|
02/11/2017
|
State Government may attend to the shortcomings mentioned in the attached document.
|
|
|
23
|
DFO (Narendranagar,Munikireti)
|
EDS
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
07/11/2017
|
State Government may attend to the shortcomings mentioned in the attached document.
|
|
|
24
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
REPLY
|
DFO (Narendranagar,Munikireti)
|
24/01/2018
|
The correction have been made as per the instruction received
|
|
|
25
|
DFO (Narendranagar,Munikireti)
|
EDS
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
31/01/2018
|
CA area is not marked in the SoI toposheet map uploaded at para-13 of para-II online.
|
|
|
26
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
REPLY
|
DFO (Narendranagar,Munikireti)
|
01/02/2018
|
The correction have been made as per the instruction received
|
|
|
27
|
DFO (Narendranagar,Munikireti)
|
EDS
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
06/02/2018
|
CA Toposheet upload in para 13 iii.
|
|
|
28
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
REPLY
|
DFO (Narendranagar,Munikireti)
|
22/02/2018
|
The correction have been made as per the instruction received
|
|
|
29
|
DFO (Narendranagar,Munikireti)
|
EDS
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
16/03/2018
|
CA Toposheet upload in para 13 iii.
|
|
|
30
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
REPLY
|
DFO (Narendranagar,Munikireti)
|
10/04/2018
|
The correction have been made as per the instruction received
|
|
|
31
|
DFO (Narendranagar,Munikireti)
|
EDS
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
27/04/2018
|
CA Toposheet upload in para 13 iii.
|
|
|
32
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
REPLY
|
DFO (Narendranagar,Munikireti)
|
08/05/2018
|
The correction have been made as per the instruction received
|
|
|
33
|
DFO (Narendranagar,Munikireti)
|
EDS
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
16/05/2018
|
CA Toposheet upload in para 13 iii.
|
|
|
34
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
REPLY
|
DFO (Narendranagar,Munikireti)
|
19/05/2018
|
The correction have been made as per the instruction received
|
|
|
35
|
DFO (Narendranagar,Munikireti)
|
REPLY
|
CF (Bhagirathi)
|
21/07/2018
|
Sir,objection cleared,please find the atteched pdf file.
|
|
|
36
|
CF (Bhagirathi)
|
REPLY
|
Nodal Officer
|
31/07/2018
|
Sir,
The correction has been done as per instruction received.
|
|
|
37
|
Nodal Officer
|
EDS
|
CF (Bhagirathi)
|
03/08/2018
|
find the letter attached
|
|
|
38
|
CF (Bhagirathi)
|
EDS
|
DFO (Narendranagar,Munikireti)
|
04/08/2018
|
find the letter attached.
|
|
|
39
|
DFO (Narendranagar,Munikireti)
|
EDS
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
09/08/2018
|
find the letter attached.
|
|
|
40
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
REPLY
|
DFO (Narendranagar,Munikireti)
|
10/08/2018
|
The correction have been made as per the instruction received
|
|
|
41
|
DFO (Narendranagar,Munikireti)
|
EDS
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
12/09/2018
|
Please Provide Original Document of FRA Certificate, Digital Maps, Land Schedule, CA certificate as per according to point no. 1
|
|
|
42
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
REPLY
|
DFO (Narendranagar,Munikireti)
|
25/09/2018
|
The correction have been made as per the instruction received
|
|
|
43
|
DFO (Narendranagar,Munikireti)
|
REPLY
|
CF (Bhagirathi)
|
27/09/2018
|
The correction have been made as per the instruction received
|
|
|
44
|
CF (Bhagirathi)
|
REPLY
|
Nodal Officer
|
09/10/2018
|
sir, the correction has been done as per instruction received.
|
|
|
45
|
CF (Bhagirathi)
|
REPLY
|
Nodal Officer
|
09/10/2018
|
sir, the correction has been done as per instruction received.
|
|
|
46
|
Nodal Officer
|
REPLY
|
State secretary
|
17/10/2018
|
Sir, The correction has been done as per instruction received.
|
|
|
47
|
State secretary
|
REPLY
|
Regional Office
|
18/10/2018
|
Sir, The correction has been done as per instruction received.
|
|