| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
08/08/2022
|
Submit the hard copy of the proposal
|
|
|
2
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
12/08/2022
|
Submit the hard copy of the proposal C.F. OFFICE.
|
|
|
3
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
01/11/2022
|
The correction have been made as per the instruction received
|
|
|
4
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
01/11/2022
|
Submit the hard copy of the proposal
|
|
|
5
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
03/11/2022
|
find the letter attached
|
|
|
6
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
05/11/2022
|
Do needful action as per EDS
|
|
|
7
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
07/11/2022
|
Do needful action as per EDS
|
|
|
8
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
17/01/2023
|
The correction have been made as per the instruction received
|
|
|
9
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
20/01/2023
|
plz find enclosed
|
|
|
10
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
09/02/2023
|
As per letter no 2137/12-1 dated 01-02-2023
|
|
|
11
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
10/02/2023
|
• • The hard copy of EDS is containing original documents is not yet received in this office.
|
|
|
12
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
16/02/2023
|
Hard copy already send by speed post
|
|
|
13
|
Regional Office
|
EDS
|
State secretary
|
20/04/2023
|
State Govt is requested to attend the shortcomings as per the letter attached.
|
|
|
14
|
State secretary
|
EDS
|
Nodal Officer
|
25/04/2023
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
|
15
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
25/04/2023
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
|
16
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
26/04/2023
|
May attend the following shortcomings as per the attachment here
|
|
|
17
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
28/04/2023
|
May attend the following shortcomings as per the attachment here
|
|
|
18
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
06/10/2023
|
The correction have been made as per the instruction received
|
|
|
19
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
09/11/2023
|
plz find enclosed.
|
|
|
20
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
18/11/2023
|
Send back
|
|
|
21
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
18/11/2023
|
plz find enclosed.
|
|
|
22
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
30/11/2023
|
As per letter no 1283/12-1 dated 17-11-2023
|
|
|
23
|
Nodal Officer
|
REPLY
|
State secretary
|
19/01/2024
|
find the letter attached
|
|
|
24
|
State secretary
|
REPLY
|
Regional Office
|
20/01/2024
|
The correction have been made as per the instruction received
|
|
|
25
|
Regional Office
|
EDS
|
State secretary
|
26/04/2024
|
State Govt is requested to attend the shortcomings as per the letter attached.
|
|
|
26
|
State secretary
|
EDS
|
Nodal Officer
|
07/05/2024
|
the attachment is not found
|
|
|
27
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
07/05/2024
|
State Govt. may attend the following shortcomings as per the attachment here.
|
|
|
28
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
10/05/2024
|
please provide the letter.
|
|
|
29
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
30/05/2024
|
find the letter attached
|
|
|
30
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
01/06/2024
|
find the letter attached
|
|
|
31
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
04/06/2024
|
find the letter attached
|
|
|
32
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
27/06/2024
|
The correction have been made as per the instruction received
|
|
|
33
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
12/07/2024
|
plz find enclosed.
|
|
|
34
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
22/07/2024
|
send back
|
|
|
35
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
22/07/2024
|
plz find enclosed
|
|
|
36
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
29/07/2024
|
As per letter no 228/12-1 dated 20-07-2024
|
|
|
37
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
03/08/2024
|
As per attachment
|
|
|
38
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
07/08/2024
|
As per attachment
|
|
|
39
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
11/09/2024
|
As per attachment
|
|
|
40
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
05/12/2024
|
The correction have been made as per the instruction received
|
|
|
41
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
12/12/2024
|
plz find enclosed.
|
|
|
42
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
23/12/2024
|
As Per Letter No- 1506/12 -1-2
Dated- 19/12/2024
|
|
|
43
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
27/01/2025
|
please upload annexures with eds reply.
|
|
|
44
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
28/01/2025
|
please upload annexures with eds reply.
|
|
|
45
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
30/01/2025
|
plz find enclosed.
|
|
|
46
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
31/01/2025
|
plz find enclosed.
|
|
|
47
|
Nodal Officer
|
REPLY
|
State secretary
|
05/02/2025
|
As per attachment
|
|
|
48
|
State secretary
|
EDS
|
Nodal Officer
|
27/02/2025
|
Please re-upload the relevant file and scan the file correctly. Unable to open the file.
|
|
|
49
|
Nodal Officer
|
REPLY
|
State secretary
|
05/04/2025
|
As per attached file
|
|
|
50
|
State secretary
|
REPLY
|
Regional Office
|
17/04/2025
|
As per attachment
|
|
|
51
|
Regional Office
|
EDS
|
State secretary
|
01/05/2025
|
EDS
|
|
|
52
|
State secretary
|
EDS
|
Nodal Officer
|
01/05/2025
|
EDS
|
|
|
53
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
11/06/2025
|
User Agency may attend the following shortcomings as per the attachment here.
|
|
|
54
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
12/06/2025
|
User Agency may attend the following shortcomings as per the attachment here.
|
|
|
55
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
27/10/2025
|
plz find enclosed
|
|
|
56
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
28/10/2025
|
User Agency may attend the following shortcomings as per the attachment here.
|
|
|
57
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
28/10/2025
|
plz find enclosed
|
|
|
58
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
15/12/2025
|
Objection are removed
|
|
|
59
|
Nodal Officer
|
REPLY
|
State secretary
|
15/12/2025
|
As per the attachment
|
|
|
60
|
State secretary
|
EDS
|
Nodal Officer
|
06/01/2026
|
Kindly re-forward the concerned proposal with all necessary documents.
|
|
|
61
|
Nodal Officer
|
REPLY
|
State secretary
|
13/01/2026
|
As per attachment
|
|