TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UK/ROAD/154869/2022              (ii). Name of Project for which Forest Land is required : Construction of road from Km 15 of BaijnathBageshwar motor road to Udalgaon in District Bageshwar              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Presently the villagers (01 number of villagers of Udalgaon with the population of 373) have to walk through a distance of 2-3 km to meet their daily needs, as there is no road connecting the village,. Due to the non-existing of any road connectivity, the lives of the villagers are in constant dang              (iv). File no. : 8B/UCP/06/40/2023/FC              (v). State : Uttarakhand              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.261
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/UK/ROAD/154869/202226/04/2022aa26/04/2022   29/06/2022 Bageshwar :01/07/2022North Kumaun:
  26/07/2022 (Bageshwar)

Uttarakhand:
02/11/2022
Uttarakhand:
21/02/2023
Dehradun:
29/03/2023
31/08/2023
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Dehradun) on:28/04/2023  
Replied by State Government(Uttarakhand) on:07/08/2023  
Query raised by State Government (Uttarakhand) on:10/05/2023  
Replied by Nodal Officer (Uttarakhand) on:07/08/2023  
Query raised by Nodal Officer (Uttarakhand) on:03/11/2022  
Replied by Circle(North Kumaun) on:08/02/2023  
Query raised by Nodal Officer (Uttarakhand) on:10/02/2023  
Replied by Circle(North Kumaun) on:16/02/2023  
Query raised by Nodal Officer (Uttarakhand) on:11/05/2023  
Replied by Circle(North Kumaun) on:22/07/2023  
Query raised by Circle (North Kumaun) on:08/08/2022  
Replied by DFO (Bageshwar) on:01/11/2022  
Query raised by Circle (North Kumaun) on:05/11/2022  
Replied by DFO (Bageshwar) on:20/01/2023  
Query raised by Circle (North Kumaun) on:12/05/2023  
Replied by DFO (Bageshwar) on:06/07/2023  
Query raised by DFO (Bageshwar) on:12/08/2022  
Replied by UA on :01/11/2022  
Query raised by DFO (Bageshwar) on:07/11/2022  
Replied by UA on :17/01/2023  
Query raised by DFO (Bageshwar) on:16/05/2023  
Replied by UA on :01/07/2023  
NOTE:- Stage-I Approval accorded by : Regional Office .