Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
08/08/2022
|
Submit the hard copy of the proposal
|
|
2
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
12/08/2022
|
Submit the hard copy of the proposal C.F office.
|
|
3
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
01/11/2022
|
The correction have been made as per the instruction received
|
|
4
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
01/11/2022
|
Submit the hard copy of the proposal.
|
|
5
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
03/11/2022
|
find the letter attached
|
|
6
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
05/11/2022
|
Do needful action as per EDS
|
|
7
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
07/11/2022
|
Do needful action as per EDS
|
|
8
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
17/01/2023
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
20/01/2023
|
plz find enclosed.
|
|
10
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
08/02/2023
|
As per letter no 2103/12-1 dated 31-01-2023
|
|
11
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
10/02/2023
|
• • The hard copy of EDS is containing original documents is not yet received in this office.
|
|
12
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
16/02/2023
|
Hard copy already send by speed post
As per letter no 2103/12-1 dated 31-01-2023
|
|
13
|
Regional Office
|
EDS
|
State secretary
|
28/04/2023
|
State govt. may attend the following shortcomings as per the attachment here
|
|
14
|
State secretary
|
EDS
|
Nodal Officer
|
10/05/2023
|
The proposal was discussed in the FRCM held on 28 April 2023. State Govt is requested to attend the shortcomings as per the FRCM MoM attached herewith.
|
|
15
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
11/05/2023
|
The proposal was discussed in the FRCM held on 28 April 2023. State Govt is requested to attend the shortcomings as per the FRCM MoM attached herewith.
|
|
16
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
12/05/2023
|
Please attend the shortcomings as per the FRCM MoM attached herewith.
|
|
17
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
16/05/2023
|
Please attend the shortcomings as per the FRCM MoM attached herewith.
|
|
18
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
01/07/2023
|
The correction have been made as per the instruction received
|
|
19
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
06/07/2023
|
plz find enclosed.
|
|
20
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
22/07/2023
|
As per letter no 138/12-1 dated 19-07-2023
|
|
21
|
Nodal Officer
|
REPLY
|
State secretary
|
07/08/2023
|
find the letter attached
|
|
22
|
State secretary
|
REPLY
|
Regional Office
|
07/08/2023
|
Dear sir/madam, please find the attachment.
|
|