TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UK/ROAD/148101/2021              (ii). Name of Project for which Forest Land is required : Patal Bhuvneshwer Dola Nani Shitla Simayal moter Road              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : patal Bhuwaneshwar, Makar gow, Nanishitala, Simayal Chamachour, ,moter Road which Will be connect five villege so the all Villagers willget comfertable short route to tehsil and distt. HQs,              (iv). State : Uttarakhand              (v). Category of the Project : Road              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 4.905
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/UK/ROAD/148101/202107/10/2021aa08/10/2021   25/10/2021 Pithoragarh :25/10/2021North Kumaun:
  08/11/2021 (Pithoragarh)

Uttarakhand:
17/11/2021
Uttarakhand:
04/02/2023
Dehradun:
14/02/2023
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Dehradun) on:16/03/2023  
Replied by State Government(Uttarakhand) on:20/01/2024  
Query raised by Regional Office (Dehradun) on:09/02/2024  
Replied by State Government(Uttarakhand) on:19/09/2024  
Query raised by State Government (Uttarakhand) on:22/03/2023  
Replied by Nodal Officer (Uttarakhand) on:19/01/2024  
Query raised by State Government (Uttarakhand) on:12/02/2024  
Replied by Nodal Officer (Uttarakhand) on:16/09/2024  
Query raised by Nodal Officer (Uttarakhand) on:01/12/2021  
Replied by Circle(North Kumaun) on:20/06/2022  
Query raised by Nodal Officer (Uttarakhand) on:05/07/2022  
Replied by Circle(North Kumaun) on:18/01/2023  
Query raised by Nodal Officer (Uttarakhand) on:24/03/2023  
Replied by Circle(North Kumaun) on:08/01/2024  
Query raised by Nodal Officer (Uttarakhand) on:12/02/2024  
Replied by Circle(North Kumaun) on:20/08/2024  
Query raised by Circle (North Kumaun) on:09/11/2021  
Replied by DFO (Pithoragarh) on:10/11/2021  
Query raised by Circle (North Kumaun) on:17/11/2021  
Replied by DFO (Pithoragarh) on:17/11/2021  
Query raised by Circle (North Kumaun) on:02/12/2021  
Replied by DFO (Pithoragarh) on:10/06/2022  
Query raised by Circle (North Kumaun) on:14/07/2022  
Replied by DFO (Pithoragarh) on:26/12/2022  
Query raised by Circle (North Kumaun) on:27/03/2023  
Replied by DFO (Pithoragarh) on:06/12/2023  
Query raised by Circle (North Kumaun) on:13/02/2024  
Replied by DFO (Pithoragarh) on:30/07/2024  
Query raised by DFO (Pithoragarh) on:29/10/2021  
Replied by UA on :30/10/2021  
Query raised by DFO (Pithoragarh) on:03/12/2021  
Replied by UA on :25/02/2022  
Query raised by DFO (Pithoragarh) on:02/03/2022  
Replied by UA on :08/03/2022  
Query raised by DFO (Pithoragarh) on:15/03/2022  
Replied by UA on :24/03/2022  
Query raised by DFO (Pithoragarh) on:25/03/2022  
Replied by UA on :31/03/2022  
Query raised by DFO (Pithoragarh) on:04/04/2022  
Replied by UA on :12/04/2022  
Query raised by DFO (Pithoragarh) on:18/07/2022  
Replied by UA on :29/11/2022  
Query raised by DFO (Pithoragarh) on:15/12/2022  
Replied by UA on :19/12/2022  
Query raised by DFO (Pithoragarh) on:01/04/2023  
Replied by UA on :01/12/2023  
Query raised by DFO (Pithoragarh) on:27/02/2024  
Replied by UA on :28/05/2024  
Query raised by DFO (Pithoragarh) on:02/07/2024  
Replied by UA on :20/07/2024  
NOTE:- Proposal is pending at Regional Office .