Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (pwdtharali@gmail.com)
|
07/09/2021
|
Please remove the objection.
|
|
2
|
User Agency (pwdtharali@gmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
15/07/2023
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (pwdtharali@gmail.com)
|
21/08/2023
|
Please remove the objection.
|
|
4
|
User Agency (pwdtharali@gmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
17/10/2023
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (pwdtharali@gmail.com)
|
22/11/2023
|
Please remove the objection
|
|
6
|
User Agency (pwdtharali@gmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
22/11/2023
|
The correction have been made as per the instruction received
|
|
7
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
22/12/2023
|
The hard copy of the proposal containing original documents is not yet received in this office.
|
|
8
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (pwdtharali@gmail.com)
|
30/01/2024
|
Please remove the objection
|
|
9
|
User Agency (pwdtharali@gmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
22/02/2024
|
The correction have been made as per the instruction received
|
|
10
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (pwdtharali@gmail.com)
|
23/02/2024
|
please remove the objection.
|
|
11
|
User Agency (pwdtharali@gmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
10/04/2024
|
The correction have been made as per the instruction received
|
|
12
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
12/04/2024
|
sir eds objection has been removed by user agency.
|
|
13
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
15/04/2024
|
Please recheck the uploaded document which is not related proposal. upload the correct document for particular proposal.
|
|
14
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
16/04/2024
|
EDS objection has been removed.
|
|
15
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
22/04/2024
|
Please recheck the uploaded document which is not related proposal. upload the correct document for particular proposal.
|
|
16
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
23/04/2024
|
sir, eds objection has been removed.
|
|
17
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
25/04/2024
|
Sir Please remove the objection
|
|
18
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
21/05/2024
|
Sir, eds objection has been removed.
|
|
19
|
Nodal Officer
|
EDS
|
CF (Garhwal)
|
30/05/2024
|
• The hard copy of the proposal containing original documents is not yet received in this office. The DFO may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part ii as in online web portal.
|
|
20
|
CF (Garhwal)
|
REPLY
|
Nodal Officer
|
03/06/2024
|
From this office letter no 2331/12-1 dated 28-05-2024, 02 hard copies of the above case have been sent to your office.
|
|
21
|
Nodal Officer
|
EDS
|
CF (Garhwal)
|
28/08/2024
|
As per attachment
|
|
22
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
31/08/2024
|
As per attachment
|
|
23
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (pwdtharali@gmail.com)
|
05/11/2024
|
Please remove the objection.
|
|
24
|
User Agency (pwdtharali@gmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
21/11/2024
|
The correction have been made as per the instruction received
|
|