TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UK/ROAD/144679/2021              (ii). Name of Project for which Forest Land is required : New Construction of Marh Marsholi to Sangatta Motor Road              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : New Construction of Marh Marsholi to Sangatta Motor Road under State Sector started from KM 2.000 of Marh Marsholi M/R and ends in KM 6.000 of Aincholi Barabey M/R through Khainal Gaon, Dabari Khainal, Dabari Joshi, Dabari villages which are TOK villages of Marsholi Bhat Gram Sabha. More than 225 p              (iv). State : Uttarakhand              (v). Category of the Project : Road              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 0.945
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/UK/ROAD/144679/202112/07/2021aa14/07/2021   12/08/2021 Pithoragarh :17/08/2021North Kumaun:
  06/09/2021 (Pithoragarh)

Uttarakhand:
14/09/2021
Uttarakhand:
03/11/2022
Dehradun:
28/11/2022
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Dehradun) on:15/12/2022  
Query raised by State Government (Uttarakhand) on:16/12/2022  
Query raised by Nodal Officer (Uttarakhand) on:17/09/2021  
Replied by Circle(North Kumaun) on:08/08/2022  
Query raised by Nodal Officer (Uttarakhand) on:23/08/2022  
Replied by Circle(North Kumaun) on:19/10/2022  
Query raised by Nodal Officer (Uttarakhand) on:16/12/2022  
Replied by Circle() on:  
Query raised by Circle (North Kumaun) on:01/10/2021  
Replied by DFO (Pithoragarh) on:18/07/2022  
Query raised by Circle (North Kumaun) on:29/08/2022  
Replied by DFO (Pithoragarh) on:13/09/2022  
Query raised by Circle (North Kumaun) on:17/12/2022  
Replied by DFO (Pithoragarh) on:26/10/2024  
Query raised by Circle (North Kumaun) on:06/11/2024  
Replied by DFO (Pithoragarh) on:19/11/2024  
Query raised by Circle (North Kumaun) on:30/11/2024  
Replied by DFO () on:  
Query raised by DFO (Pithoragarh) on:21/08/2021  
Replied by UA on :04/09/2021  
Query raised by DFO (Pithoragarh) on:01/10/2021  
Replied by UA on :06/07/2022  
Query raised by DFO (Pithoragarh) on:19/12/2022  
Replied by UA on :17/02/2023  
Query raised by DFO (Pithoragarh) on:25/02/2023  
Replied by UA on :05/04/2023  
Query raised by DFO (Pithoragarh) on:25/04/2023  
Replied by UA on :25/10/2023  
Query raised by DFO (Pithoragarh) on:01/12/2023  
Replied by UA on :02/06/2024  
Query raised by DFO (Pithoragarh) on:06/06/2024  
Replied by UA on :26/10/2024  
NOTE:- Proposal is pending at DFO due to EDS raised by Regional Office .