  (i). Proposal No. : FP/UK/ROAD/120677/2021              (ii). Name of Project for which Forest Land is required : Construction of Panyapodi Toli Gwalgaon Motor Road 7.750 Km              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Construction of Panyapodi Toli Gwalgaon Motor Road give the connectivity to all villagers of Toli(Gwalgaon) with Tanakpur-Twaghat motor road. Length of the motor road is 7.750 Km.              (iv). File no. : 8B/UCP/06/60/2022/FC              (v). State : Uttarakhand              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 3.875
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/UK/ROAD/120677/202125/01/2021aa28/01/2021   06/03/2021 Pithoragarh :08/03/2021North Kumaun:
  17/03/2021 (Pithoragarh)

Uttarakhand:
06/04/2021
Uttarakhand:
18/08/2022
Dehradun:
30/08/2022
25/10/2023
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Dehradun) on:15/09/2022  
Replied by State Government(Uttarakhand) on:05/10/2023  
Query raised by State Government (Uttarakhand) on:16/09/2022  
Replied by Nodal Officer (Uttarakhand) on:05/10/2023  
Query raised by Nodal Officer (Uttarakhand) on:15/04/2021  
Replied by Circle(North Kumaun) on:10/05/2021  
Query raised by Nodal Officer (Uttarakhand) on:02/06/2021  
Replied by Circle(North Kumaun) on:26/07/2021  
Query raised by Nodal Officer (Uttarakhand) on:29/07/2021  
Replied by Circle(North Kumaun) on:29/07/2022  
Query raised by Nodal Officer (Uttarakhand) on:16/09/2022  
Replied by Circle(North Kumaun) on:23/09/2023  
Query raised by Circle (North Kumaun) on:18/03/2021  
Replied by DFO (Pithoragarh) on:25/03/2021  
Query raised by Circle (North Kumaun) on:15/04/2021  
Replied by DFO (Pithoragarh) on:06/05/2021  
Query raised by Circle (North Kumaun) on:07/06/2021  
Replied by DFO (Pithoragarh) on:23/07/2021  
Query raised by Circle (North Kumaun) on:31/07/2021  
Replied by DFO (Pithoragarh) on:05/07/2022  
Query raised by Circle (North Kumaun) on:19/09/2022  
Replied by DFO (Pithoragarh) on:19/08/2023  
Query raised by DFO (Pithoragarh) on:19/03/2021  
Replied by UA on :23/03/2021  
Query raised by DFO (Pithoragarh) on:16/04/2021  
Replied by UA on :20/04/2021  
Query raised by DFO (Pithoragarh) on:09/06/2021  
Replied by UA on :17/06/2021  
Query raised by DFO (Pithoragarh) on:22/06/2021  
Replied by UA on :18/07/2021  
Query raised by DFO (Pithoragarh) on:31/07/2021  
Replied by UA on :23/06/2022  
Query raised by DFO (Pithoragarh) on:28/09/2022  
Replied by UA on :30/05/2023  
Query raised by DFO (Pithoragarh) on:17/06/2023  
Replied by UA on :17/08/2023  