TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UK/ROAD/119756/2021              (ii). Name of Project for which Forest Land is required : sanbend san syund to saterakhal Motor road              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : the proposal is created to join the village syund and its sub villages thala and some others having total population 313. with road connectivity villagers will get benefits of many govt facilities.              (iv). File no. : 8B/UCP/06/94/2021/FC              (v). State : Uttarakhand              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.958
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/UK/ROAD/119756/202116/01/202119/01/2021   10/02/2021   11/02/2021   18/02/2021 Rudraprayag :18/02/2021Garhwal:
  16/08/2021 (Rudraprayag)

Uttarakhand:
28/08/2021
Uttarakhand:
13/09/2021
Dehradun:
21/09/2021
06/12/2021
By :Regional Office
Uttarakhand
19/05/2023
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Dehradun) on:18/10/2021  
Replied by State Government(Uttarakhand) on:13/01/2022  
Query raised by State Government (Uttarakhand) on:21/10/2021  
Replied by Nodal Officer (Uttarakhand) on:13/01/2022  
Query raised by Nodal Officer (Uttarakhand) on:21/10/2021  
Replied by Circle(Garhwal) on:06/01/2022  
Query raised by Circle (Garhwal) on:22/10/2021  
Replied by DFO (Rudraprayag) on:30/12/2021  
Query raised by DFO (Rudraprayag) on:09/03/2021  
Replied by UA on :18/03/2021  
Query raised by DFO (Rudraprayag) on:31/03/2021  
Replied by UA on :22/04/2021  
Query raised by DFO (Rudraprayag) on:21/06/2021  
Replied by UA on :29/06/2021  
Query raised by DFO (Rudraprayag) on:01/07/2021  
Replied by UA on :26/07/2021  
Query raised by DFO (Rudraprayag) on:26/10/2021  
Replied by UA on :23/11/2021  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by Regional Office (Dehradun) on:14/06/2023  
Query raised by State Government (Uttarakhand) on:14/06/2023  
Query raised by Nodal Officer on:14/06/2023  
Replied by UA on :22/11/2024  
NOTE:- Proposal is pending at Nodal Officer after receiving Compliance of Conditions due to EDS raised by RO for Stage-II .