Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Narendranagar,Munikireti)
|
EDS
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
11/08/2015
|
Attached the Query Detail
|
|
2
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
REPLY
|
DFO (Narendranagar,Munikireti)
|
14/08/2015
|
Answer of Query Related with Additional Info
|
|
3
|
DFO (Narendranagar,Munikireti)
|
EDS
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
31/08/2015
|
Please CA Estamate Fresh Copy Upload
|
|
4
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
REPLY
|
DFO (Narendranagar,Munikireti)
|
02/09/2015
|
CA Estimate
|
|
5
|
Nodal Officer
|
EDS
|
CF (Bhagirathi)
|
30/09/2015
|
1.Please review entry in serial no. 4,6,7,12,13 of Form A Part II 2. Please enter Revenue Forests for Civil soyam forests in serial no.2 regarding legal status of forests
|
|
6
|
CF (Bhagirathi)
|
EDS
|
DFO (Narendranagar,Munikireti)
|
08/10/2015
|
1.Please review entry in serial no. 4,6,7,12,13 of Form A Part II 2. Please enter Revenue Forests for Civil soyam forests in serial no.2 regarding legal status of forests
|
|
7
|
DFO (Narendranagar,Munikireti)
|
EDS
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
12/10/2015
|
1.Please review entry in serial no. 4,6,7,12,13 of Form A Part II 2. Please enter Revenue Forests for Civil soyam forests in serial no.2 regarding legal status of forests
|
|
8
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
REPLY
|
DFO (Narendranagar,Munikireti)
|
15/10/2015
|
The objections relate to entries to be done by DFO
|
|
9
|
DFO (Narendranagar,Munikireti)
|
REPLY
|
CF (Bhagirathi)
|
21/10/2015
|
Sir,
On Line EDS Complete
|
|
10
|
CF (Bhagirathi)
|
REPLY
|
Nodal Officer
|
28/10/2015
|
Online objection clarify by Dfo narendranagar.
|
|
11
|
Regional Office
|
EDS
|
State secretary
|
06/11/2015
|
The online proposal is returned back since hard copy has not been submitted to this office simultaneously. State Govt. may resubmit the proposal online after hard copy has been provided in Regional Office. As a proof scanned copy of the receipt of hard copy from the Regional Office may also be uploaded along with online proposal. Attached Letter No. Misc./II/ROC/COP/1/2013/1846 Dated 06.11.2015 may also be referred in this regard.
|
|
12
|
State secretary
|
EDS
|
Nodal Officer
|
07/11/2015
|
Plz reply to obj of RO-The online proposal is returned back since hard copy has not been submitted to this office simultaneously. State Govt. may resubmit the proposal online after hard copy has been provided in Regional Office. As a proof scanned copy of the receipt of hard copy from the Regional Office may also be uploaded along with online proposal. Attached Letter No. Misc./II/ROC/COP/1/2013/1846 Dated 06.11.2015 may also be referred in this regard.
|
|
13
|
Nodal Officer
|
EDS
|
CF (Bhagirathi)
|
09/11/2015
|
Plz reply to obj of RO-The online proposal is returned back since hard copy has not been submitted to this office simultaneously. State Govt. may resubmit the proposal online after hard copy has been provided in Regional Office. As a proof scanned copy of the receipt of hard copy from the Regional Office may also be uploaded along with online proposal. Attached Letter No. Misc./II/ROC/COP/1/2013/1846 Dated 06.11.2015 may also be referred in this regard.
|
|
14
|
CF (Bhagirathi)
|
REPLY
|
Nodal Officer
|
09/12/2015
|
EDS Reply Attached all docoments
|
|
15
|
Nodal Officer
|
REPLY
|
State secretary
|
02/01/2016
|
As desired, as per your on-line query dated 07-11-2015, receipt of submission of hard copy of the proposal by nodal office to the RO FRI, is attached here with.
|
|
16
|
State secretary
|
REPLY
|
Regional Office
|
04/01/2016
|
As desired, as per your on-line query dated 07-11-2015, receipt of submission of hard copy of the proposal by nodal office to the RO FRI, is attached here with.
|
|
17
|
Regional Office
|
EDS
|
State secretary
|
06/01/2016
|
1. Short narrative for the project is not given properly.
Authority letter is not signed and not issued for the applicant Mr Bhagwati Prasad Nautiyal.
3. Village wise breakup is not given in part I.
4. Name of components is not shown in Part I.
5. Employment generation details is not provided in Part I.
6. The area marked for muck disposal is in civil land and naap land but it is not clear that the area is included in the area proposed for diversion or not and for the area marked in naap land, necessary NOCs are not provided.
7. The details of trees involved are 90 as per Part II but in hard copy it is 103, need clarification.
8. 1 no. of tree is shown in protected forest as per details in hard copy, whereas no protected forest is involve in the proposed diversion, need clarificati
|
|
18
|
State secretary
|
EDS
|
Nodal Officer
|
07/01/2016
|
Plz reply to obj of RO-1. Short narrative for the project is not given properly. Authority letter is not signed and not issued for the applicant Mr Bhagwati Prasad Nautiyal. 3. Village wise breakup is not given in part I. 4. Name of components is not shown in Part I. 5. Employment generation details is not provided in Part I. 6. The area marked for muck disposal is in civil land and naap land but it is not clear that the area is included in the area proposed for diversion or not and for the area marked in naap land, necessary NOCs are not provided. 7. The details of trees involved are 90 as per Part II but in hard copy it is 103, need clarification. 8. 1 no. of tree is shown in protected forest as per details in hard copy, whereas no protected forest is involve in the proposed diversion, n
|
|
19
|
Nodal Officer
|
EDS
|
CF (Bhagirathi)
|
11/01/2016
|
Plz reply to obj of RO-1. Short narrative for the project is not given properly. Authority letter is not signed and not issued for the applicant Mr Bhagwati Prasad Nautiyal. 3. Village wise breakup is not given in part I. 4. Name of components is not shown in Part I. 5. Employment generation details is not provided in Part I. 6. The area marked for muck disposal is in civil land and naap land but it is not clear that the area is included in the area proposed for diversion or not and for the area marked in naap land, necessary NOCs are not provided. 7. The details of trees involved are 90 as per Part II but in hard copy it is 103, need clarification. 8. 1 no. of tree is shown in protected forest as per details in hard copy, whereas no protected forest is involve in the proposed diversion,
|
|
20
|
CF (Bhagirathi)
|
EDS
|
DFO (Narendranagar,Munikireti)
|
12/01/2016
|
Plz reply to obj of RO-1. Short narrative for the project is not given properly. Authority letter is not signed and not issued for the applicant Mr Bhagwati Prasad Nautiyal. 3. Village wise breakup is not given in part I. 4. Name of components is not shown in Part I. 5. Employment generation details is not provided in Part I. 6. The area marked for muck disposal is in civil land and naap land but it is not clear that the area is included in the area proposed for diversion or not and for the area marked in naap land, necessary NOCs are not provided. 7. The details of trees involved are 90 as per Part II but in hard copy it is 103, need clarification. 8. 1 no. of tree is shown in protected forest as per details in hard copy, whereas no protected forest is involve in the proposed diversion,
|
|
21
|
DFO (Narendranagar,Munikireti)
|
EDS
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
12/01/2016
|
Plz reply to obj of RO-1. Short narrative for the project is not given properly. Authority letter is not signed and not issued for the applicant Mr Bhagwati Prasad Nautiyal. 3. Village wise breakup is not given in part I. 4. Name of components is not shown in Part I. 5. Employment generation details is not provided in Part I. 6. The area marked for muck disposal is in civil land and naap land but it is not clear that the area is included in the area proposed for diversion or not and for the area marked in naap land, necessary NOCs are not provided. 7. The details of trees involved are 90 as per Part II but in hard copy it is 103, need clarification. 8. 1 no. of tree is shown in protected forest as per details in hard copy, whereas no protected forest is involve in the proposed diversion,
|
|
22
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
REPLY
|
DFO (Narendranagar,Munikireti)
|
26/02/2016
|
The correction have been made as per the instruction received
|
|
23
|
DFO (Narendranagar,Munikireti)
|
EDS
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
29/02/2016
|
Plz. Point Wise Detail Enclosed.
|
|
24
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
REPLY
|
DFO (Narendranagar,Munikireti)
|
05/03/2016
|
Point Wise Detail Enclosed.
|
|
25
|
DFO (Narendranagar,Munikireti)
|
EDS
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
08/03/2016
|
8. 1 no. of tree is shown in protected forest as per details in hard copy, whereas no protected forest is involve in the proposed diversion.
|
|
26
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
REPLY
|
DFO (Narendranagar,Munikireti)
|
05/04/2016
|
The correction have been made as per the instruction received
|
|
27
|
DFO (Narendranagar,Munikireti)
|
EDS
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
08/04/2016
|
8. 1 no. of tree is shown in protected forest as per details in hard copy, whereas no protected forest is involve in the proposed diversion. Please Attach The Certificate.
|
|
28
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
REPLY
|
DFO (Narendranagar,Munikireti)
|
18/04/2016
|
The correction have been made as per the instruction received
|
|
29
|
DFO (Narendranagar,Munikireti)
|
EDS
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
19/04/2016
|
Please Attach The Certificate.
|
|
30
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
REPLY
|
DFO (Narendranagar,Munikireti)
|
25/04/2016
|
The correction have been made as per the instruction received
|
|
31
|
DFO (Narendranagar,Munikireti)
|
REPLY
|
CF (Bhagirathi)
|
26/04/2016
|
The correction have been made as per instruction.
|
|
32
|
CF (Bhagirathi)
|
EDS
|
DFO (Narendranagar,Munikireti)
|
05/05/2016
|
Plz reply to obj of RO-1. Short narrative for the project is not given properly. Authority letter is not signed and not issued for the applicant Mr Bhagwati Prasad Nautiyal. 3. Village wise breakup is not given in part I. 4. Name of components is not shown in Part I. 5. Employment generation details is not provided in Part I. 6. The area marked for muck disposal is in civil land and naap land but it is not clear that the area is included in the area proposed for diversion or not and for the area marked in naap land, necessary NOCs are not provided. 7. The details of trees involved are 90 as per Part II but in hard copy it is 103, need clarification. 8. 1 no. of tree is shown in protected forest as per details in hard copy, whereas no protected forest is involve in the proposed diversion,
|
|
33
|
DFO (Narendranagar,Munikireti)
|
EDS
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
05/05/2016
|
Plz reply to obj of RO-1. Short narrative for the project is not given properly. Authority letter is not signed and not issued for the applicant Mr Bhagwati Prasad Nautiyal. 3. Village wise breakup is not given in part I. 4. Name of components is not shown in Part I. 5. Employment generation details is not provided in Part I. 6. The area marked for muck disposal is in civil land and naap land but it is not clear that the area is included in the area proposed for diversion or not and for the area marked in naap land, necessary NOCs are not provided. 7. The details of trees involved are 90 as per Part II but in hard copy it is 103, need clarification. 8. 1 no. of tree is shown in protected forest as per details in hard copy, whereas no protected forest is involve in the proposed diversion,
|
|
34
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
REPLY
|
DFO (Narendranagar,Munikireti)
|
10/05/2016
|
The correction have been made as per the instruction received
|
|
35
|
DFO (Narendranagar,Munikireti)
|
REPLY
|
CF (Bhagirathi)
|
18/05/2016
|
Sir the correction have been made as per the instruction. PDF file attached.
|
|
36
|
CF (Bhagirathi)
|
EDS
|
DFO (Narendranagar,Munikireti)
|
27/05/2016
|
Attachment Pdf Covering letter does not shown clearly. So Plz Attach clear Attachment again
|
|
37
|
DFO (Narendranagar,Munikireti)
|
EDS
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
07/06/2016
|
Attachment Pdf Covering letter does not shown clearly. So Plz Attach clear Attachment again
|
|
38
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
REPLY
|
DFO (Narendranagar,Munikireti)
|
23/06/2016
|
The correction have been made as per the instruction received
|
|
39
|
DFO (Narendranagar,Munikireti)
|
EDS
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
20/08/2016
|
Reply with Attachment.
|
|
40
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
REPLY
|
DFO (Narendranagar,Munikireti)
|
29/08/2016
|
The correction have been made as per the instruction received
|
|
41
|
DFO (Narendranagar,Munikireti)
|
EDS
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
02/09/2016
|
Please give me point wise reply with All Document.
|
|
42
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
REPLY
|
DFO (Narendranagar,Munikireti)
|
05/09/2016
|
The correction have been made as per the instruction received
|
|
43
|
DFO (Narendranagar,Munikireti)
|
EDS
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
12/09/2016
|
Please give me point wise reply with All Document.
|
|
44
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
REPLY
|
DFO (Narendranagar,Munikireti)
|
12/09/2016
|
The correction have been made as per the instruction received
|
|
45
|
DFO (Narendranagar,Munikireti)
|
REPLY
|
CF (Bhagirathi)
|
15/09/2016
|
Sir, Correction have been made as per the instruction received.
|
|
46
|
CF (Bhagirathi)
|
REPLY
|
Nodal Officer
|
16/09/2016
|
sir, correction have been made as per the instruction.
|
|
47
|
Nodal Officer
|
EDS
|
CF (Bhagirathi)
|
20/09/2016
|
Reply is improper and does not correspond to the queries raised by regional office. CF may provide detailed point wise reply along with corrections and numbered annexure in support of the same.
|
|
48
|
CF (Bhagirathi)
|
EDS
|
DFO (Narendranagar,Munikireti)
|
21/09/2016
|
Reply is improper and does not correspond to the queries raised by regional office. Dfo may provide detailed point wise reply along with corrections and numbered annexure in support of the same.
|
|
49
|
DFO (Narendranagar,Munikireti)
|
REPLY
|
CF (Bhagirathi)
|
22/09/2016
|
Point Wise Detail attached here.
1- Annexure-(1) 1Page.
2- Annexure-(2) 9Pages.
3- Annexure-(3) 1Page.
|
|
50
|
CF (Bhagirathi)
|
REPLY
|
Nodal Officer
|
22/09/2016
|
Sir,
Point Wise Detail attached as a Pdf file.
|
|
51
|
Nodal Officer
|
EDS
|
CF (Bhagirathi)
|
22/09/2016
|
Reply is improper and does not correspond to the queries raised by regional office. CF may provide detailed point wise reply along with corrections and numbered annexure in support of the same.
|
|
52
|
CF (Bhagirathi)
|
EDS
|
DFO (Narendranagar,Munikireti)
|
24/09/2016
|
Reply is improper and does not correspond to the queries raised by regional office. DFO may provide detailed point wise reply along with corrections and numbered annexure in support of the same.
|
|
53
|
DFO (Narendranagar,Munikireti)
|
REPLY
|
CF (Bhagirathi)
|
27/09/2016
|
Point Wise Reply as per Instruction.
|
|
54
|
CF (Bhagirathi)
|
REPLY
|
Nodal Officer
|
28/09/2016
|
sir, we have cleared your objection as per the instructions.
|
|
55
|
Nodal Officer
|
EDS
|
CF (Bhagirathi)
|
30/09/2016
|
Reply is improper and does not correspond to the queries raised by regional office. CF may provide detailed point wise reply along with corrections and numbered annexure in support of the same.
|
|
56
|
CF (Bhagirathi)
|
EDS
|
DFO (Narendranagar,Munikireti)
|
30/09/2016
|
Reply is improper and does not correspond to the queries raised by regional office. DFO may provide detailed point wise reply along with corrections and numbered annexure in support of the same.
|
|
57
|
DFO (Narendranagar,Munikireti)
|
EDS
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
30/09/2016
|
Reply is improper and does not correspond to the queries raised by regional office. U.A may provide detailed point wise reply along with corrections and numbered annexure in support of the same.
|
|
58
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
REPLY
|
DFO (Narendranagar,Munikireti)
|
30/09/2016
|
The correction have been made as per the instruction received
|
|
59
|
DFO (Narendranagar,Munikireti)
|
REPLY
|
CF (Bhagirathi)
|
30/09/2016
|
The Correction have been made as pet the instruction received,
|
|
60
|
CF (Bhagirathi)
|
EDS
|
DFO (Narendranagar,Munikireti)
|
01/10/2016
|
Reply is improper and does not correspond to the queries raised by regional office. DFO may provide detailed point wise reply along with corrections and numbered annexure in support of the same.
|
|
61
|
DFO (Narendranagar,Munikireti)
|
REPLY
|
CF (Bhagirathi)
|
01/10/2016
|
The Correction have been made as pet the instruction received,
|
|
62
|
CF (Bhagirathi)
|
REPLY
|
Nodal Officer
|
04/10/2016
|
Sir,
Attach a Pdf after Clarifying objection.
|
|
63
|
Nodal Officer
|
EDS
|
CF (Bhagirathi)
|
05/10/2016
|
Point wise reply received from CF is being attached herewith with consent.
|
|
64
|
CF (Bhagirathi)
|
REPLY
|
Nodal Officer
|
18/10/2016
|
Sir
Attach a Pdf after clarify Objection.
|
|
65
|
Nodal Officer
|
REPLY
|
State secretary
|
21/10/2016
|
Point wise reply received from CF is being attached herewith with consent.
|
|
66
|
State secretary
|
REPLY
|
Regional Office
|
08/11/2016
|
Point wise reply received from CF is being attached herewith with consent.
|
|
67
|
Regional Office
|
EDS
|
State secretary
|
17/11/2016
|
with reference to your letter dated 8-11-2016 I am directed to inform you that following shortcomings are still remained in the proposal are attached with this EDS.
|
|
68
|
State secretary
|
EDS
|
Nodal Officer
|
22/11/2016
|
with reference to your letter dated 8-11-2016 I am directed to inform you that following shortcomings are still remained in the proposal are attached with this EDS.
|
|
69
|
Nodal Officer
|
EDS
|
CF (Bhagirathi)
|
30/11/2016
|
with reference to your letter dated 8-11-2016 I am directed to inform you that following shortcomings are still remained in the proposal are attached with this EDS.
|
|
70
|
CF (Bhagirathi)
|
EDS
|
DFO (Narendranagar,Munikireti)
|
01/12/2016
|
Clarify Objection raised by nodal officer.
|
|
71
|
DFO (Narendranagar,Munikireti)
|
EDS
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
09/12/2016
|
Clarify Objection raised by nodal officer.
|
|
72
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
REPLY
|
DFO (Narendranagar,Munikireti)
|
10/12/2016
|
The correction have been made as per the instruction received
|
|
73
|
DFO (Narendranagar,Munikireti)
|
EDS
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
20/12/2016
|
employment Detail provided in online part-1 is appears to be incorrect.
|
|
74
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
REPLY
|
DFO (Narendranagar,Munikireti)
|
20/12/2016
|
The correction have been made as per the instruction received
|
|
75
|
DFO (Narendranagar,Munikireti)
|
REPLY
|
CF (Bhagirathi)
|
23/12/2016
|
Sir Point Wise EDS Reply Attached as per instruction received.
|
|
76
|
CF (Bhagirathi)
|
REPLY
|
Nodal Officer
|
26/12/2016
|
Sir,
Attach a Pdf after clarify Objection.
|
|
77
|
Nodal Officer
|
REPLY
|
State secretary
|
27/12/2016
|
ShortComing in the proposal are removed as per enclosed attachemnt.
|
|
78
|
State secretary
|
REPLY
|
Regional Office
|
28/12/2016
|
ShortComing in the proposal are removed as per enclosed attachemnt.
|
|
79
|
Regional Office
|
EDS
|
State secretary
|
25/01/2017
|
the shortcomings are still remained in the proposal for which find the letter attached.
|
|
80
|
State secretary
|
EDS
|
Nodal Officer
|
30/01/2017
|
the shortcomings are still remained in the proposal for which find the letter attached.
|
|
81
|
Nodal Officer
|
EDS
|
CF (Bhagirathi)
|
30/01/2017
|
the shortcomings are still remained in the proposal for which find the letter attached.
|
|
82
|
CF (Bhagirathi)
|
EDS
|
DFO (Narendranagar,Munikireti)
|
01/02/2017
|
The shortcomings are still remained in the proposal for which find the letter attached.
|
|
83
|
DFO (Narendranagar,Munikireti)
|
EDS
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
06/02/2017
|
The shortcomings are still remained in the proposal for which find the letter attached.
|
|
84
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
REPLY
|
DFO (Narendranagar,Munikireti)
|
27/03/2017
|
The correction have been made as per the instruction received
|
|
85
|
DFO (Narendranagar,Munikireti)
|
EDS
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
01/04/2017
|
The shortcomings are still remained in the proposal for which find the letter attached.
|
|
86
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
REPLY
|
DFO (Narendranagar,Munikireti)
|
05/04/2017
|
The correction have been made as per the instruction received
|
|
87
|
DFO (Narendranagar,Munikireti)
|
EDS
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
13/04/2017
|
Please Provide us Original copy of revised document according to Point No.02
|
|
88
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
REPLY
|
DFO (Narendranagar,Munikireti)
|
05/05/2017
|
The correction have been made as per the instruction received
|
|
89
|
DFO (Narendranagar,Munikireti)
|
REPLY
|
CF (Bhagirathi)
|
12/05/2017
|
Sir Correction have been made as per instruction received.
|
|
90
|
CF (Bhagirathi)
|
REPLY
|
Nodal Officer
|
07/06/2017
|
Sir,
Attach a Pdf after clarify Objection.
|
|
91
|
Nodal Officer
|
EDS
|
CF (Bhagirathi)
|
16/06/2017
|
find the letter attached
|
|
92
|
CF (Bhagirathi)
|
EDS
|
DFO (Narendranagar,Munikireti)
|
19/06/2017
|
find the letter attachment and clarify Objection raised by Nodal Officer.
|
|
93
|
DFO (Narendranagar,Munikireti)
|
EDS
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
22/06/2017
|
find the letter attachment and clarify Objection raised by Nodal Officer.
|
|
94
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
REPLY
|
DFO (Narendranagar,Munikireti)
|
27/06/2017
|
The correction have been made as per the instruction received
|
|
95
|
DFO (Narendranagar,Munikireti)
|
EDS
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
11/07/2017
|
Please Provide us Hard copy of Revised Document.
|
|
96
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
REPLY
|
DFO (Narendranagar,Munikireti)
|
20/07/2017
|
The correction have been made as per the instruction received
|
|
97
|
DFO (Narendranagar,Munikireti)
|
REPLY
|
CF (Bhagirathi)
|
28/07/2017
|
Sir correction have been made as per the instruction received
|
|
98
|
CF (Bhagirathi)
|
REPLY
|
Nodal Officer
|
05/09/2017
|
Objection clear as per attachment PDF file.
|
|
99
|
Nodal Officer
|
EDS
|
CF (Bhagirathi)
|
16/09/2017
|
the shortcomings are still remained in the proposal for which find the letter attached.
|
|
100
|
CF (Bhagirathi)
|
EDS
|
DFO (Narendranagar,Munikireti)
|
20/09/2017
|
Sir, please attached the file
|
|
101
|
DFO (Narendranagar,Munikireti)
|
EDS
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
27/09/2017
|
please attached the file
|
|
102
|
User Agency (eepwdkirtinagar@rediffmail.com)
|
REPLY
|
DFO (Narendranagar,Munikireti)
|
26/10/2017
|
The correction have been made as per the instruction received
|
|
103
|
DFO (Narendranagar,Munikireti)
|
REPLY
|
CF (Bhagirathi)
|
07/11/2017
|
Sir the Correction have been made as per the instruction received.
|
|
104
|
CF (Bhagirathi)
|
EDS
|
DFO (Narendranagar,Munikireti)
|
16/11/2017
|
Sir,
Attach a PDF after clarify Objection.
|
|
105
|
DFO (Narendranagar,Munikireti)
|
REPLY
|
CF (Bhagirathi)
|
16/11/2017
|
Sir, Attach a PDF after clarify Objection.
|
|
106
|
CF (Bhagirathi)
|
REPLY
|
Nodal Officer
|
16/11/2017
|
Sir,
Attach a PDF after clarify Objection.
|
|
107
|
Nodal Officer
|
REPLY
|
State secretary
|
27/11/2017
|
the asked queries have been corrected and attach herewith in Eds Letter column.
|
|
108
|
State secretary
|
REPLY
|
Regional Office
|
30/11/2017
|
the shortcomings are still remained in the proposal for which find the letter attached.
|
|