TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UK/ROAD/10120/2015              (ii). Name of Project for which Forest Land is required : Construction of Gogena Kimu Motor Road(7.00 Km)              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Construction of Gogena Kimu Motor Road(7.00 Km)              (iv). File no. : 1(396)/2016              (v). State : Uttarakhand              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 2.45
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/UK/ROAD/10120/201514/02/201501/06/2016  03/01/2016  21/11/2015  28/06/2015  11/06/2015  26/04/2015  05/04/2015  28/03/2015  23/03/2015  22/03/2015  15/03/2015  07/03/2015  22/02/2015  16/02/2015  15/02/2015  14/02/2015   04/07/2016  29/04/2016  22/11/2015  17/08/2015  26/06/2015  13/05/2015  18/04/2015  31/03/2015  24/03/2015  23/03/2015  18/03/2015  09/03/2015  26/02/2015  19/02/2015  16/02/2015  14/02/2015   18/07/2016   20/07/2016 Bageshwar :17/08/2016North Kumaun:
  19/09/2016 (Bageshwar)

Uttarakhand:
21/09/2016
Uttarakhand:
30/09/2016
04/11/2016
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Bageshwar) on:26/08/2016  
Replied by UA on :11/09/2016  
NOTE:- Stage-I Approval accorded by : State Government .