Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Almora)
|
EDS
|
User Agency (ajayanand@vtlrewa.com)
|
28/03/2019
|
please provide hard copy of the proposal in Dfo office as soon as possible dated 28-03-2019
|
|
2
|
User Agency (ajayanand@vtlrewa.com)
|
REPLY
|
DFO (Almora)
|
30/03/2019
|
The correction have been made as per the instruction received
|
|
3
|
CF (North Kumaun)
|
EDS
|
DFO (Almora)
|
19/06/2019
|
As per letter no 6027/12-1 dated 18-06-2019
|
|
4
|
DFO (Almora)
|
REPLY
|
CF (North Kumaun)
|
01/08/2019
|
objection reply date 1-08-2019
|
|
5
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
07/08/2019
|
CF may clarify, whatever this RoW --right of way-- has approved under FC clearance at the time of construction
|
|
6
|
CF (North Kumaun)
|
EDS
|
DFO (Almora)
|
08/08/2019
|
As per letter no 529/12-1 dated 08-08-2019
|
|
7
|
DFO (Almora)
|
REPLY
|
CF (North Kumaun)
|
20/08/2019
|
objection reply dated 20-08-2019
|
|
8
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
21/08/2019
|
As per letter no 744/12-1 dated 21-08-2019
|
|