Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UK/Others/33453/2018              (ii). Name of Project for which Forest Land is required : Chakrata kalsi OFC kalsi -lohari              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Laying of Optical Fibre Cable (OFC) along with road at Hill Side on NH-123(New-507) (Herbertpur-Nainbagh road) SH-20 (Kalsi-Makhti Road) NH- 707A (Chakrata-Lohari Road) Total km. 94.00 &0.9486 Ha.              (iv). File no. : 2(15)/2019              (v). State : Uttarakhand              (vi). Category of the Project : Others              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.68
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/UK/Others/33453/201816/05/201828/05/2018   02/06/2018   06/06/2018   03/07/2018 Chakrata :21/09/2018Yamuna:
  22/10/2018 (Chakrata)

Uttarakhand:
15/11/2018
Uttarakhand:
14/03/2019
26/04/2019
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Nodal Officer (Uttarakhand) on:01/12/2018  
Replied by Circle(Yamuna) on:05/01/2019  
Query raised by Circle (Yamuna) on:29/10/2018  
Replied by DFO (Chakrata) on:29/10/2018  
Query raised by Circle (Yamuna) on:05/11/2018  
Replied by DFO (Chakrata) on:12/11/2018  
Query raised by Circle (Yamuna) on:01/12/2018  
Replied by DFO (Chakrata) on:01/01/2019  
Query raised by DFO (Chakrata) on:22/09/2018  
Replied by UA on :10/10/2018  
Query raised by DFO (Chakrata) on:03/12/2018  
Replied by UA on :11/12/2018  
NOTE:- Stage-I Approval accorded by : State Government .