Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Uttarkashi)
|
EDS
|
User Agency (ajayanand@vtlrewa.com)
|
10/01/2018
|
Objection as per attachment PDF file.
|
|
2
|
User Agency (ajayanand@vtlrewa.com)
|
REPLY
|
DFO (Uttarkashi)
|
07/02/2018
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Uttarkashi)
|
EDS
|
User Agency (ajayanand@vtlrewa.com)
|
16/02/2018
|
Objection as per attachment PDF file.
|
|
4
|
User Agency (ajayanand@vtlrewa.com)
|
REPLY
|
DFO (Uttarkashi)
|
19/02/2018
|
The correction have been made as per the instruction received
|
|
5
|
Nodal Officer
|
EDS
|
CF (Bhagirathi)
|
08/05/2018
|
The hard copy of the proposal containing original documents is not yet received in this office. The user agency may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part iii as in online web portal.
|
|
6
|
CF (Bhagirathi)
|
EDS
|
DFO (Uttarkashi)
|
09/05/2018
|
The hard copy of the proposal containing original documents is not yet received in this office. The user agency may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part iii as in online web portal.
|
|
7
|
DFO (Uttarkashi)
|
EDS
|
User Agency (ajayanand@vtlrewa.com)
|
10/05/2018
|
The hard copy of the proposal containing original documents is not yet received in this office. The user agency may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part iii as in online web portal.
|
|
8
|
User Agency (ajayanand@vtlrewa.com)
|
REPLY
|
DFO (Uttarkashi)
|
26/05/2018
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Uttarkashi)
|
REPLY
|
CF (Bhagirathi)
|
28/05/2018
|
Sir, Hard copy of the proposal containing original documents is already Nodal Office received. Received Letter attachment in PDF file.
|
|
10
|
CF (Bhagirathi)
|
REPLY
|
Nodal Officer
|
28/05/2018
|
Sir,
Hard copy of the proposal containing original documents is already Nodal Office received. Received Letter attachment in PDF file.
|
|
11
|
Nodal Officer
|
EDS
|
CF (Bhagirathi)
|
23/06/2018
|
find the letter attached
|
|
12
|
CF (Bhagirathi)
|
EDS
|
DFO (Uttarkashi)
|
25/06/2018
|
Find the letter attached and clarify the objection raised by nodal officer.
|
|
13
|
DFO (Uttarkashi)
|
EDS
|
User Agency (ajayanand@vtlrewa.com)
|
27/06/2018
|
Find the letter attached and clarify the objection raised by nodal officer.
|
|
14
|
User Agency (ajayanand@vtlrewa.com)
|
REPLY
|
DFO (Uttarkashi)
|
16/03/2019
|
The correction have been made as per the instruction received
|
|
15
|
DFO (Uttarkashi)
|
EDS
|
User Agency (ajayanand@vtlrewa.com)
|
25/03/2019
|
Find the letter attached and clarify the objection raised by Nodal officer.
|
|
16
|
User Agency (ajayanand@vtlrewa.com)
|
REPLY
|
DFO (Uttarkashi)
|
27/03/2019
|
The correction have been made as per the instruction received
|
|
17
|
DFO (Uttarkashi)
|
REPLY
|
CF (Bhagirathi)
|
27/03/2019
|
Sir, Objection as per attachment to PDF file.
|
|
18
|
CF (Bhagirathi)
|
REPLY
|
Nodal Officer
|
28/03/2019
|
sir, the shortcomings have been resolved as per attached letter of DFO.
|
|
19
|
Nodal Officer
|
EDS
|
CF (Bhagirathi)
|
02/04/2019
|
user agency. may attend the shortcomings as per attachment.
|
|
20
|
CF (Bhagirathi)
|
EDS
|
DFO (Uttarkashi)
|
05/04/2019
|
user agency. may attend the shortcomings as per attachment.
|
|
21
|
DFO (Uttarkashi)
|
EDS
|
User Agency (ajayanand@vtlrewa.com)
|
05/04/2019
|
user agency. may attend the shortcomings as per attachment.
|
|
22
|
User Agency (ajayanand@vtlrewa.com)
|
REPLY
|
DFO (Uttarkashi)
|
27/04/2019
|
The correction have been made as per the instruction received
|
|
23
|
DFO (Uttarkashi)
|
REPLY
|
CF (Bhagirathi)
|
03/06/2019
|
sir , the shortcomings have been resolved as per letter attached.
|
|
24
|
CF (Bhagirathi)
|
REPLY
|
Nodal Officer
|
03/06/2019
|
Shortcomings have been resolved as per attached letter of DFO.
|
|
25
|
Nodal Officer
|
EDS
|
CF (Bhagirathi)
|
03/07/2019
|
CF may clarify, whatever this RoW --right of way-- has approved under FC clearance at the time of construction
|
|
26
|
CF (Bhagirathi)
|
EDS
|
DFO (Uttarkashi)
|
08/07/2019
|
DFO may clarify, whatever this RoW --right of way-- has approved under FC clearance at the time of construction
|
|
27
|
DFO (Uttarkashi)
|
REPLY
|
CF (Bhagirathi)
|
12/07/2019
|
Sir, Objection as per attachment to PDF file.
|
|
28
|
CF (Bhagirathi)
|
REPLY
|
Nodal Officer
|
17/07/2019
|
Plz Find the letter Attached.
|
|