Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Nainital)
|
EDS
|
User Agency (gitesh.duggal@idea.adityabirla.com)
|
23/05/2017
|
EDS Reply
|
|
2
|
User Agency (gitesh.duggal@idea.adityabirla.com)
|
REPLY
|
DFO (Nainital)
|
02/06/2017
|
The correction have been made as per the instruction received
|
|
3
|
Nodal Officer
|
EDS
|
CF (South Kumaun)
|
12/06/2017
|
The hard copy of the proposal containing original documents is not yet received in this office. The State Govt may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part V as in online web portal.
|
|
4
|
CF (South Kumaun)
|
REPLY
|
Nodal Officer
|
15/06/2017
|
already summit hard copy by user agency in nodal office
|
|
5
|
Nodal Officer
|
EDS
|
CF (South Kumaun)
|
19/06/2017
|
find the letter attached
|
|
6
|
CF (South Kumaun)
|
EDS
|
DFO (Nainital)
|
21/06/2017
|
find the letter attached
|
|
7
|
DFO (Nainital)
|
EDS
|
User Agency (gitesh.duggal@idea.adityabirla.com)
|
21/06/2017
|
find the letter attached
|
|
8
|
User Agency (gitesh.duggal@idea.adityabirla.com)
|
REPLY
|
DFO (Nainital)
|
22/06/2017
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Nainital)
|
EDS
|
User Agency (gitesh.duggal@idea.adityabirla.com)
|
22/06/2017
|
Nodal officer EDS point No 3 Bar Chart with index not cleare
|
|
10
|
User Agency (gitesh.duggal@idea.adityabirla.com)
|
REPLY
|
DFO (Nainital)
|
27/06/2017
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Nainital)
|
REPLY
|
CF (South Kumaun)
|
30/06/2017
|
EDS Reply
|
|
12
|
CF (South Kumaun)
|
REPLY
|
Nodal Officer
|
03/07/2017
|
as per your on line query dated 19-06-2017. DFO Nainital informed that user agency complete all the queries a letter of DFO enclosed here with.
|
|