Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Dehradun)
|
EDS
|
User Agency (tarit.mohan@ril.com)
|
03/06/2019
|
please all document
|
|
2
|
User Agency (tarit.mohan@ril.com)
|
REPLY
|
DFO (Dehradun)
|
03/06/2019
|
The correction have been made as per the instruction received
|
|
3
|
CF (Shivalik)
|
EDS
|
DFO (Dehradun)
|
13/06/2019
|
plz find the attachment
|
|
4
|
DFO (Dehradun)
|
EDS
|
User Agency (tarit.mohan@ril.com)
|
15/06/2019
|
Point wise question and answer
|
|
5
|
User Agency (tarit.mohan@ril.com)
|
REPLY
|
DFO (Dehradun)
|
28/06/2019
|
The correction have been made as per the instruction received
|
|
6
|
DFO (Dehradun)
|
REPLY
|
CF (Shivalik)
|
02/07/2019
|
The correction have been made.
|
|
7
|
CF (Shivalik)
|
EDS
|
DFO (Dehradun)
|
03/07/2019
|
DFO may clarify Query No. 2
|
|
8
|
DFO (Dehradun)
|
REPLY
|
CF (Shivalik)
|
03/07/2019
|
The correction have been made.
|
|
9
|
Nodal Officer
|
EDS
|
CF (Shivalik)
|
03/07/2019
|
CF may clarify, whatever this RoW --right of way-- has approved under FC clearance at the time of construction
|
|
10
|
CF (Shivalik)
|
EDS
|
DFO (Dehradun)
|
04/07/2019
|
DFO may clarify, whatever this RoW --right of way-- has approved under FC clearance at the time of construction
|
|
11
|
DFO (Dehradun)
|
REPLY
|
CF (Shivalik)
|
09/07/2019
|
The correction have been made.
|
|
12
|
CF (Shivalik)
|
REPLY
|
Nodal Officer
|
09/07/2019
|
The correction have been made as per instruction received.
|
|