TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UK/MIN/38285/2019              (ii). Name of Project for which Forest Land is required : Collection of Minor Minerals From Song 1, 2, 3 and Jakhan 1, 2 of Dehradun Forest division              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : During monsoon RBM got collected in the river course which lead to flooding of the river. By extracting this RBM from the river bed flooding can be prevented. this activity is prescribed in working plan of Derhadun Forest Division.              (iv). File no. : 8-62/1999-FC vol.              (v). State : Uttarakhand              (vi). Category of the Project : Mining              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 628.8
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentMoEFCC,New DelhiRegional Office(SIR) uploaded onStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/UK/MIN/38285/201922/01/201925/01/2019   26/01/2019   06/02/2019   15/02/2019 Dehradun :26/03/2019Shivalik:
  20/05/2019 (Dehradun)

Uttarakhand:
03/07/2019
Uttarakhand:
18/09/2019
23/09/201905/11/2019
02/12/2019
04/02/2021
By :Head Office
Uttarakhand
15/06/2021
20/10/2021
By :Head Office
  
C. Essential Details Sought History
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by MoEFCC,New Delhi on 09/01/2020  
Replied by State Government (Uttarakhand) on:25/08/2020  
Query raised by MoEFCC,New Delhi on 09/09/2020  
Replied by State Government (Uttarakhand) on:21/11/2020  
Query raised by State Government (Uttarakhand) on:10/01/2020  
Replied by Nodal Officer (Uttarakhand) on:25/08/2020  
Query raised by State Government (Uttarakhand) on:10/09/2020  
Replied by Nodal Officer (Uttarakhand) on:12/10/2020  
Query raised by State Government (Uttarakhand) on:21/10/2020  
Replied by Nodal Officer (Uttarakhand) on:22/10/2020  
Query raised by State Government (Uttarakhand) on:28/10/2020  
Replied by Nodal Officer (Uttarakhand) on:21/11/2020  
Query raised by Nodal Officer (Uttarakhand) on:08/07/2019  
Replied by Circle(Shivalik) on:19/08/2019  
Query raised by Nodal Officer (Uttarakhand) on:20/08/2019  
Replied by Circle(Shivalik) on:05/09/2019  
Query raised by Nodal Officer (Uttarakhand) on:13/01/2020  
Replied by Circle(Shivalik) on:30/07/2020  
Query raised by Nodal Officer (Uttarakhand) on:10/09/2020  
Replied by Circle(Shivalik) on:10/10/2020  
Query raised by Nodal Officer (Uttarakhand) on:28/10/2020  
Replied by Circle(Shivalik) on:21/11/2020  
Query raised by Circle (Shivalik) on:24/05/2019  
Replied by DFO (Dehradun) on:04/06/2019  
Query raised by Circle (Shivalik) on:10/06/2019  
Replied by DFO (Dehradun) on:21/06/2019  
Query raised by Circle (Shivalik) on:08/07/2019  
Replied by DFO (Dehradun) on:09/08/2019  
Query raised by Circle (Shivalik) on:20/08/2019  
Replied by DFO (Dehradun) on:03/09/2019  
Query raised by Circle (Shivalik) on:03/09/2019  
Replied by DFO (Dehradun) on:03/09/2019  
Query raised by Circle (Shivalik) on:13/01/2020  
Replied by DFO (Dehradun) on:27/07/2020  
Query raised by Circle (Shivalik) on:11/09/2020  
Replied by DFO (Dehradun) on:07/10/2020  
Query raised by Circle (Shivalik) on:29/10/2020  
Replied by DFO (Dehradun) on:20/11/2020  
Query raised by DFO (Dehradun) on:25/05/2019  
Replied by UA on :31/05/2019  
Query raised by DFO (Dehradun) on:11/07/2019  
Replied by UA on :18/07/2019  
Query raised by DFO (Dehradun) on:22/08/2019  
Replied by UA on :26/08/2019  
Query raised by DFO (Dehradun) on:18/01/2020  
Replied by UA on :02/07/2020  
Query raised by DFO (Dehradun) on:11/08/2020  
Replied by UA on :14/08/2020  
Query raised by DFO (Dehradun) on:13/09/2020  
Replied by UA on :26/09/2020  
Query raised by DFO (Dehradun) on:29/10/2020  
Replied by UA on :08/11/2020  
Query raised by DFO (Dehradun) on:18/11/2020  
Replied by UA on :19/11/2020  
Query raised by DFO (Dehradun) on:19/11/2020  
Replied by UA on :19/11/2020  
D. Essential Details Sought History (Stage-II)
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by MoEFCC,New Delhi 15/07/2021  
Replied by State Government (Uttarakhand) on:07/09/2021  
Query raised by State Government (Uttarakhand) on:11/08/2021  
Replied by Nodal Officer (Uttarakhand) on:04/09/2021  
Query raised by Nodal Officer on:03/09/2021  
Replied by UA on :04/09/2021  
NOTE:- Stage-II Approval accorded by : Head Office .