Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Ramnagar)
|
EDS
|
User Agency (ucupreti64@gmail.com)
|
05/08/2022
|
Plz do the needful as per the letter Attached.
|
|
2
|
User Agency (ucupreti64@gmail.com)
|
REPLY
|
DFO (Ramnagar)
|
24/08/2022
|
The correction have been made as per the instruction received
|
|
3
|
Nodal Officer
|
EDS
|
CF (Western)
|
29/09/2022
|
• The hard copy of the proposal containing original documents is not yet received in this office. The CF may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part iii as in online web portal.
|
|
4
|
CF (Western)
|
REPLY
|
Nodal Officer
|
04/10/2022
|
Hard copy of the proposal has been submitted as letter attached. Please do the needful.
|
|
5
|
Regional Office
|
EDS
|
State secretary
|
30/12/2022
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
6
|
State secretary
|
EDS
|
Nodal Officer
|
31/12/2022
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
7
|
Nodal Officer
|
EDS
|
CF (Western)
|
31/12/2022
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
8
|
CF (Western)
|
EDS
|
DFO (Ramnagar)
|
31/12/2022
|
As per letter attached, Kindly do the needful.
|
|
9
|
DFO (Ramnagar)
|
EDS
|
User Agency (ucupreti64@gmail.com)
|
06/01/2023
|
As per letter attached, Kindly do the needful.
|
|
10
|
User Agency (ucupreti64@gmail.com)
|
REPLY
|
DFO (Ramnagar)
|
20/01/2023
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Ramnagar)
|
EDS
|
User Agency (ucupreti64@gmail.com)
|
30/01/2023
|
Please Provide the areial Distance certificate from national park, wildlife corridor, wildlife sanctuary.
|
|
12
|
User Agency (ucupreti64@gmail.com)
|
REPLY
|
DFO (Ramnagar)
|
20/12/2023
|
The correction have been made as per the instruction received
|
|
13
|
DFO (Ramnagar)
|
EDS
|
User Agency (ucupreti64@gmail.com)
|
22/12/2023
|
Plz Upload the latest KML
|
|
14
|
User Agency (ucupreti64@gmail.com)
|
REPLY
|
DFO (Ramnagar)
|
22/12/2023
|
The correction have been made as per the instruction received
|
|
15
|
DFO (Ramnagar)
|
REPLY
|
CF (Western)
|
23/12/2023
|
Shortcomings has been rectified as letter attached. Kindly do the needful.
|
|
16
|
CF (Western)
|
REPLY
|
Nodal Officer
|
12/01/2024
|
As per EDS necessary shortcomings has been rectified as letter attached. Please do the needful.
|
|
17
|
Nodal Officer
|
REPLY
|
State secretary
|
01/02/2024
|
As per EDS necessary shortcomings has been rectified as letter attached. Please do the needful.
|
|
18
|
State secretary
|
REPLY
|
Regional Office
|
06/02/2024
|
As per EDS necessary shortcomings has been rectified as letter attached. Please do the needful.
|
|
19
|
Regional Office
|
EDS
|
State secretary
|
31/05/2024
|
State Government is requested to attend the shortcomings as per the document attached.
|
|
20
|
State secretary
|
EDS
|
Nodal Officer
|
07/06/2024
|
Kindly attend to the Query raised by RO.
|
|
21
|
Nodal Officer
|
EDS
|
CF (Western)
|
15/06/2024
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
22
|
CF (Western)
|
EDS
|
DFO (Ramnagar)
|
19/06/2024
|
As per letter attached, kindly do the needful.
|
|
23
|
DFO (Ramnagar)
|
REPLY
|
CF (Western)
|
19/06/2024
|
As per instruction given necessary shortcomings has been rectified.
|
|
24
|
CF (Western)
|
EDS
|
DFO (Ramnagar)
|
19/06/2024
|
Kindly do the needful.
|
|
25
|
DFO (Ramnagar)
|
EDS
|
User Agency (ucupreti64@gmail.com)
|
03/07/2024
|
Kindly do the needful.
|
|
26
|
User Agency (ucupreti64@gmail.com)
|
REPLY
|
DFO (Ramnagar)
|
09/07/2024
|
The correction have been made as per the instruction received
|
|
27
|
DFO (Ramnagar)
|
EDS
|
User Agency (ucupreti64@gmail.com)
|
26/07/2024
|
As per letter attached, kindly do the needful.
|
|
28
|
User Agency (ucupreti64@gmail.com)
|
REPLY
|
DFO (Ramnagar)
|
01/08/2024
|
The correction have been made as per the instruction received
|
|
29
|
DFO (Ramnagar)
|
REPLY
|
CF (Western)
|
01/08/2024
|
Shortcomings are rectified Plz do the Needful.
|
|
30
|
CF (Western)
|
REPLY
|
Nodal Officer
|
03/08/2024
|
Necessary shortcomings has been rectified as letter attached, kindly do the needful.
|
|
31
|
Nodal Officer
|
REPLY
|
State secretary
|
21/08/2024
|
As per nodal letter dated 21-8-2024
|
|
32
|
State secretary
|
REPLY
|
Regional Office
|
27/08/2024
|
EDS reply by nodal office
|
|