Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
Nodal Officer
|
EDS
|
CF (Villupuram)
|
20/05/2020
|
The CCF isrequestd to upload the details vide PCCF ref.No. TS3-61585-2019, dt. 20.05.2020 for further action.
|
|
2
|
CF (Villupuram)
|
EDS
|
DFO (Villupuram)
|
26/05/2020
|
For necessary corrections as received from PCCF office
|
|
3
|
DFO (Villupuram)
|
REPLY
|
CF (Villupuram)
|
26/05/2020
|
CA scheme is seen to be uploaded in DFO login. a copy of the same is attached herewith
|
|
4
|
CF (Villupuram)
|
EDS
|
DFO (Villupuram)
|
26/05/2020
|
period of recommendation has still not been corrected
|
|
5
|
DFO (Villupuram)
|
REPLY
|
CF (Villupuram)
|
26/05/2020
|
it may be considered as 30 years as requested by user agency
|
|
6
|
CF (Villupuram)
|
EDS
|
DFO (Villupuram)
|
26/05/2020
|
site suitability certificate to be uploaded. period to be mentioned in recommendation
|
|
7
|
DFO (Villupuram)
|
REPLY
|
CF (Villupuram)
|
26/05/2020
|
not able to update recommendation period
|
|
8
|
CF (Villupuram)
|
EDS
|
DFO (Villupuram)
|
26/05/2020
|
corrections still not done as per pccf query
|
|
9
|
DFO (Villupuram)
|
REPLY
|
CF (Villupuram)
|
26/05/2020
|
attached pdf with reply to queries as well as copy of CA scheme and site suitability certificate
|
|
10
|
CF (Villupuram)
|
REPLY
|
Nodal Officer
|
26/05/2020
|
Please find attach point wise details along with scanned copy of CA scheme and DFO signed site suitability certificate
|
|
11
|
Regional Office
|
EDS
|
State secretary
|
09/08/2020
|
map, revisit of component wise breakup etc
|
|
12
|
State secretary
|
EDS
|
Nodal Officer
|
14/08/2020
|
Pl refer GOI letter and rectify the defects
|
|
13
|
Nodal Officer
|
EDS
|
CF (Villupuram)
|
14/08/2020
|
Pl refer GOi letter and rectify and resubmit the proposal
|
|
14
|
CF (Villupuram)
|
EDS
|
DFO (Villupuram)
|
17/08/2020
|
Please refer to the letter received from government of India and furnish details
|
|
15
|
DFO (Villupuram)
|
EDS
|
User Agency (eepftdm@gmail.com)
|
17/08/2020
|
Please refer to the letter received from government of India and furnish details
|
|
16
|
User Agency (eepftdm@gmail.com)
|
REPLY
|
DFO (Villupuram)
|
19/08/2020
|
The correction have been made as per the instruction received
|
|
17
|
DFO (Villupuram)
|
REPLY
|
CF (Villupuram)
|
21/08/2020
|
Sir please find the replies to the GOI letter dated 14/08/20. User agency have uploaded their replies in additional details section.
|
|
18
|
CF (Villupuram)
|
REPLY
|
Nodal Officer
|
21/08/2020
|
Please find attached the replies to GOI letter as submitted by user agency and DFO for consideration.
|
|
19
|
Nodal Officer
|
EDS
|
CF (Villupuram)
|
05/09/2020
|
The CF isrequestd to upload the details vide PCCF ref.No. TS3-61585-2019, dt. 04.09.2020.
|
|
20
|
CF (Villupuram)
|
EDS
|
DFO (Villupuram)
|
17/09/2020
|
DFO to provide details as asked by PCCF office.
|
|
21
|
DFO (Villupuram)
|
EDS
|
User Agency (eepftdm@gmail.com)
|
17/09/2020
|
details as asked in reference from PCCF office to be provided
|
|
22
|
User Agency (eepftdm@gmail.com)
|
REPLY
|
DFO (Villupuram)
|
26/09/2020
|
The correction have been made as per the instruction received
|
|
23
|
DFO (Villupuram)
|
REPLY
|
CF (Villupuram)
|
29/09/2020
|
the details asked by PCCF office have been updated in the portal and new set of hard copies have been generated and put up to PCCF office.
|
|
24
|
CF (Villupuram)
|
REPLY
|
Nodal Officer
|
01/10/2020
|
As per the DFO report, necessary corrections have been made and additional documents have been uploaded in the online portal. Hard copies are also being sent.
|
|
25
|
Nodal Officer
|
REPLY
|
State secretary
|
29/10/2020
|
Additional details called for by the GOI is furnished.
|
|
26
|
State secretary
|
REPLY
|
Regional Office
|
27/11/2020
|
Additional details called for by the GOI is furnished.
|
|