TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/TN/TRANS/150320/2021              (ii). Name of Project for which Forest Land is required : Erection of 230KV DC line on MC towers by making LILO of existing Ottiyambakkam to Omega feeder - II at the proposed Mambakkam 230/110KV Substation              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : This scheme has been proposed to upgrade existing Mambakkam 110KV substation as 230/110KV Substation for which this 230KV line is proposed to erect by utilising existing 110KV corridor. The proposed new 230KV towers are being erected by dismantling and replacing old 110 kv towers in the same corrido              (iv). File no. : 4-TNB100/2023-CHN              (v). State : Tamil Nadu              (vi). Category of the Project : Transmission Line              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 4.27
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/TN/TRANS/150320/202123/12/202129/01/2022  03/01/2022   09/02/2022  11/01/2022   16/02/2022   17/02/2022 Chengalpattu,Kancheepuram :23/02/2022Chennai:
  18/04/2022 (Chengalpattu,Kancheepuram)

Tamil Nadu:
10/08/2022
Tamil Nadu:
26/12/2022
Chennai:
29/03/2023
06/11/2023
By :Regional Office
Tamil Nadu
23/10/2024
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Chennai) on:11/05/2023  
Replied by State Government(Tamil Nadu) on:15/09/2023  
Query raised by State Government (Tamil Nadu) on:07/06/2023  
Replied by Nodal Officer (Tamil Nadu) on:13/07/2023  
Query raised by Nodal Officer (Tamil Nadu) on:09/09/2022  
Replied by Circle(Chennai) on:16/09/2022  
Query raised by Nodal Officer (Tamil Nadu) on:03/10/2022  
Replied by Circle(Chennai) on:08/11/2022  
Query raised by Nodal Officer (Tamil Nadu) on:16/11/2022  
Replied by Circle(Chennai) on:06/12/2022  
Query raised by Nodal Officer (Tamil Nadu) on:12/06/2023  
Replied by Circle(Chennai) on:06/07/2023  
Query raised by Circle (Chennai) on:27/04/2022  
Replied by DFO (Chengalpattu,Kancheepuram) on:01/06/2022  
Query raised by Circle (Chennai) on:06/10/2022  
Replied by DFO (Chengalpattu,Kancheepuram) on:25/10/2022  
Query raised by Circle (Chennai) on:07/11/2022  
Replied by DFO (Chengalpattu,Kancheepuram) on:07/11/2022  
Query raised by Circle (Chennai) on:25/11/2022  
Replied by DFO (Chengalpattu,Kancheepuram) on:29/11/2022  
Query raised by Circle (Chennai) on:21/06/2023  
Replied by DFO (Chengalpattu,Kancheepuram) on:26/06/2023  
NOTE:- Proposal is pending at RO for Stage-II .