Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Dharmapuri)
|
EDS
|
User Agency (ravichandran@gail.co.in)
|
21/03/2023
|
Plz rectify the shortcomings pointed out & submit the proposal as soon as possible for forest clearance.
|
|
2
|
User Agency (ravichandran@gail.co.in)
|
REPLY
|
DFO (Dharmapuri)
|
24/03/2023
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Dharmapuri)
|
EDS
|
User Agency (ravichandran@gail.co.in)
|
28/03/2023
|
Please rectify the shortcomings pointed out for further process.
|
|
4
|
User Agency (ravichandran@gail.co.in)
|
REPLY
|
DFO (Dharmapuri)
|
24/04/2023
|
The correction have been made as per the instruction received
|
|
5
|
CF (Dharmapuri)
|
EDS
|
DFO (Dharmapuri)
|
17/05/2023
|
Short coming pointed out in CF C.No.9398/2021/D Dated.17-05-2023 may be rectified and resubmitted.
|
|
6
|
DFO (Dharmapuri)
|
EDS
|
User Agency (ravichandran@gail.co.in)
|
25/05/2023
|
Plz rectify the KML and relavant documents for further process.
|
|
7
|
User Agency (ravichandran@gail.co.in)
|
REPLY
|
DFO (Dharmapuri)
|
12/06/2023
|
The correction have been made as per the instruction received
|
|
8
|
DFO (Dharmapuri)
|
REPLY
|
CF (Dharmapuri)
|
20/06/2023
|
I Submit that, the proposal is revised as per the instructions. This may kindly be considered and forwarded for further process.
|
|
9
|
CF (Dharmapuri)
|
EDS
|
DFO (Dharmapuri)
|
21/07/2023
|
The essential details requirement and rectification called for CF in C.No.9398/2021/D Dated.21-07-2023 may be furnished for further action.
|
|
10
|
DFO (Dharmapuri)
|
EDS
|
User Agency (ravichandran@gail.co.in)
|
26/07/2023
|
Plz furnish the additional details as called for by the Conservator of Forests, Dharmapuri Circle during the field inspection on 21.07.2023.
|
|
11
|
User Agency (ravichandran@gail.co.in)
|
REPLY
|
DFO (Dharmapuri)
|
15/08/2023
|
The correction have been made as per the instruction received
|
|
12
|
DFO (Dharmapuri)
|
EDS
|
User Agency (ravichandran@gail.co.in)
|
28/08/2023
|
Plz mark on the ground completely with the stations numbered along with GPS readings for the actual area proposed for diversion to make ready the proposed area for field inspection of Conservator of Forests, Dharmapuri Circle.
|
|
13
|
User Agency (ravichandran@gail.co.in)
|
REPLY
|
DFO (Dharmapuri)
|
20/09/2023
|
The correction have been made as per the instruction received
|
|
14
|
DFO (Dharmapuri)
|
REPLY
|
CF (Dharmapuri)
|
21/09/2023
|
The actual area proposed for diversion was marked on the ground and the map containing stations numbered along with GPS readings have been uploaded in additional information details section and also furnished in the hard copy for verification during the filed inspection by Conservator of Forests, Dharmapuri Circle.
|
|
15
|
Nodal Officer
|
EDS
|
CF (Dharmapuri)
|
18/01/2024
|
The CF is requested to rectify the shortcomings and resubmit the proposal vide PCCF ref No.TS3/29849/2021 dt.18.01.2024.
|
|
16
|
CF (Dharmapuri)
|
EDS
|
DFO (Dharmapuri)
|
01/02/2024
|
The DFO is requested to rectify the shortcomings in consultation with UA and send appropriate reply early for further process.
|
|
17
|
DFO (Dharmapuri)
|
EDS
|
User Agency (ravichandran@gail.co.in)
|
05/02/2024
|
Please rectify the short comings pointed out by the Principal Chief Conservator of Forests, chennai vide Ref.No. TS3/29849/2021 dated.18.01.2024 and request you to resubmit the revised proposal at online for getting forest clearance at the earliest.
|
|
18
|
User Agency (ravichandran@gail.co.in)
|
REPLY
|
DFO (Dharmapuri)
|
06/03/2024
|
The correction have been made as per the instruction received
|
|
19
|
DFO (Dharmapuri)
|
EDS
|
User Agency (ravichandran@gail.co.in)
|
15/03/2024
|
Plz send the proposal with fullfilment of the Queries raised by the PCCF, Chennai. vide Ref.No. TS3/29849/2021 dated.18.01.2024.
|
|
20
|
User Agency (ravichandran@gail.co.in)
|
REPLY
|
DFO (Dharmapuri)
|
06/05/2024
|
The correction have been made as per the instruction received
|
|
21
|
DFO (Dharmapuri)
|
EDS
|
User Agency (ravichandran@gail.co.in)
|
10/06/2024
|
Plz furnish the additional details....
|
|
22
|
User Agency (ravichandran@gail.co.in)
|
REPLY
|
DFO (Dharmapuri)
|
25/06/2024
|
The correction have been made as per the instruction received
|
|
23
|
DFO (Dharmapuri)
|
EDS
|
User Agency (ravichandran@gail.co.in)
|
04/07/2024
|
Plz upload the letter from District Collector, Dharmapuri that the identified CA land details and tansferred to Forest Department.
|
|
24
|
User Agency (ravichandran@gail.co.in)
|
REPLY
|
DFO (Dharmapuri)
|
02/09/2024
|
The correction have been made as per the instruction received
|
|
25
|
DFO (Dharmapuri)
|
EDS
|
User Agency (ravichandran@gail.co.in)
|
19/09/2024
|
Hence, the User agency is requested to upload the KML file of the Compensatory Afforestation land identified in SF.No.692/1 of Kammampatty Village in Nallampalli Taluk of Dharmapuri District in PART I of form-A in the option provided in the Parivesh Web portal with relevant documents at the earliest.
|
|
26
|
User Agency (ravichandran@gail.co.in)
|
REPLY
|
DFO (Dharmapuri)
|
04/10/2024
|
The correction have been made as per the instruction received
|
|
27
|
DFO (Dharmapuri)
|
EDS
|
User Agency (ravichandran@gail.co.in)
|
16/10/2024
|
The User Agency is requested to send the proposal in full shape at the earliest.
|
|
28
|
User Agency (ravichandran@gail.co.in)
|
REPLY
|
DFO (Dharmapuri)
|
08/11/2024
|
The correction have been made as per the instruction received
|
|
29
|
DFO (Dharmapuri)
|
EDS
|
User Agency (ravichandran@gail.co.in)
|
13/11/2024
|
Plz make necessary arrangements for CA land field inspection and the identified CA land should be free from encroachments....
|
|
30
|
User Agency (ravichandran@gail.co.in)
|
REPLY
|
DFO (Dharmapuri)
|
10/12/2024
|
The correction have been made as per the instruction received
|
|
31
|
DFO (Dharmapuri)
|
REPLY
|
CF (Dharmapuri)
|
17/12/2024
|
I submit that, the required details are furnished by the User Agency. Thus, Considering the importance of this project. This project proposal may kindly be considered for further process.
|
|
32
|
CF (Dharmapuri)
|
REPLY
|
Nodal Officer
|
20/12/2024
|
Submit the proposal short coming pointed out by the PCCF vide vide PCCF ref No.TS3/29849/2021 dt.18.01.2024.
|
|
33
|
Nodal Officer
|
EDS
|
CF (Dharmapuri)
|
10/01/2025
|
The CF is requested to rectify the shortcomings and resubmit the proposal vide PCCF ref No.TS3/29849/2021 dt.09.01.2025.
|
|
34
|
CF (Dharmapuri)
|
EDS
|
DFO (Dharmapuri)
|
20/01/2025
|
Reply the queries immediately
|
|
35
|
DFO (Dharmapuri)
|
EDS
|
User Agency (ravichandran@gail.co.in)
|
21/01/2025
|
the User agency is requested to furnish the necessary documents in Hard copies and must be uploaded in Additional information details section for the query raised by the PCCF, Chennai. vide Ref.No. TS3/29849/2021, dated.09.01.2025.
|
|
36
|
User Agency (ravichandran@gail.co.in)
|
REPLY
|
DFO (Dharmapuri)
|
22/01/2025
|
The correction have been made as per the instruction received
|
|
37
|
DFO (Dharmapuri)
|
REPLY
|
CF (Dharmapuri)
|
22/01/2025
|
I submit the reply for the queries raised. This may kindly be considered for further process.
|
|
38
|
CF (Dharmapuri)
|
REPLY
|
Nodal Officer
|
23/01/2025
|
Recommended.
|
|