| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
DFO (Chengalpattu,Kancheepuram)
|
EDS
|
User Agency (balsamy.thirunagalingam@ril.com)
|
03/10/2023
|
joint inspection to finalize the total area proposed for diversion as the area mentioned in the proposal is varying from the actual s
|
|
|
2
|
User Agency (balsamy.thirunagalingam@ril.com)
|
REPLY
|
DFO (Chengalpattu,Kancheepuram)
|
05/02/2024
|
The correction have been made as per the instruction received
|
|
|
3
|
CF (Chennai)
|
EDS
|
DFO (Chengalpattu,Kancheepuram)
|
18/07/2024
|
impact of reserved forest.
|
|
|
4
|
DFO (Chengalpattu,Kancheepuram)
|
REPLY
|
CF (Chennai)
|
29/07/2024
|
Additional detail submitted.
|
|
|
5
|
Nodal Officer
|
EDS
|
CF (Chennai)
|
24/09/2024
|
The CCF is requested to furnish the details, vide PCCF ref NO.TS3/6769/2023 dt.23.09.2024. whether the proposed work in the admitted RoW and the proposed diversion of forest land is an fresh diversion or already diverted.
|
|
|
6
|
CF (Chennai)
|
EDS
|
DFO (Chengalpattu,Kancheepuram)
|
25/09/2024
|
Additional details called for
|
|
|
7
|
DFO (Chengalpattu,Kancheepuram)
|
REPLY
|
CF (Chennai)
|
18/10/2024
|
Additional detail submitted.
|
|
|
8
|
CF (Chennai)
|
EDS
|
DFO (Chengalpattu,Kancheepuram)
|
22/10/2024
|
Specific reply query raised
|
|
|
9
|
DFO (Chengalpattu,Kancheepuram)
|
REPLY
|
CF (Chennai)
|
29/10/2024
|
Specific report submitted.
|
|
|
10
|
CF (Chennai)
|
REPLY
|
Nodal Officer
|
07/11/2024
|
Reply to the queries raised by PCCF (HoFF)
|
|
|
11
|
Nodal Officer
|
EDS
|
CF (Chennai)
|
14/11/2024
|
The CCF Chennai is requested to inform the User Agency to furnish the consent letter -NOC vide PCCF ref No.TS3/6769/2023 dt.14.11.2024.
|
|
|
12
|
CF (Chennai)
|
EDS
|
DFO (Chengalpattu,Kancheepuram)
|
18/11/2024
|
Additional details called for
|
|
|
13
|
DFO (Chengalpattu,Kancheepuram)
|
EDS
|
User Agency (balsamy.thirunagalingam@ril.com)
|
18/11/2024
|
Additional details called for
|
|
|
14
|
User Agency (balsamy.thirunagalingam@ril.com)
|
REPLY
|
DFO (Chengalpattu,Kancheepuram)
|
07/03/2025
|
The correction have been made as per the instruction received
|
|
|
15
|
DFO (Chengalpattu,Kancheepuram)
|
EDS
|
User Agency (balsamy.thirunagalingam@ril.com)
|
22/03/2025
|
you are requested to furnish the consent letter NOC from the Primary user agency for usage of 500mtr length and 0.30mtr width area by the Secondary user agency for laying of underground OFC in the already diverted reserved forest area in favour of Primary User Agency MEPS
|
|
|
16
|
User Agency (balsamy.thirunagalingam@ril.com)
|
REPLY
|
DFO (Chengalpattu,Kancheepuram)
|
23/10/2025
|
The correction have been made as per the instruction received
|
|
|
17
|
DFO (Chengalpattu,Kancheepuram)
|
REPLY
|
CF (Chennai)
|
22/11/2025
|
User agency has submitted the NOC obtained from MEPZ SEZ
|
|
|
18
|
CF (Chennai)
|
REPLY
|
Nodal Officer
|
09/01/2026
|
submitted
|
|