Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Theni)
|
EDS
|
User Agency (balsamy.thirunagalingam@ril.com)
|
24/03/2021
|
Submit Proposal Hard Copy.
|
|
2
|
User Agency (balsamy.thirunagalingam@ril.com)
|
REPLY
|
DFO (Theni)
|
24/03/2021
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Theni)
|
EDS
|
User Agency (balsamy.thirunagalingam@ril.com)
|
12/04/2021
|
The proposed area submitted bu User Agency is 0.020Ha. but the actual area is 0.022 Ha. as per the dimensions in the proposal
i.e
1. Valkaradu RF - 373m x 0.30m is 111.90 m2
2. Paramasivankovil Karadu RL - 365m x 0.30m is 109.50m2, overall area is 221.40m2 i.e 0.022 Ha.
Hence, the User Agency is instructed to revise the proposed area accordingly.
|
|
4
|
User Agency (balsamy.thirunagalingam@ril.com)
|
REPLY
|
DFO (Theni)
|
15/04/2021
|
The correction have been made as per the instruction received
|
|
5
|
CF (Madurai)
|
EDS
|
DFO (Theni)
|
30/04/2021
|
Send further details
|
|
6
|
DFO (Theni)
|
EDS
|
User Agency (balsamy.thirunagalingam@ril.com)
|
03/05/2021
|
The User Agency is requested to report whether this proposed OFC cable will be laid along the left side or right side of towards New Bus Stand to Collector Office Road and also to confirm the depth of the trench.
|
|
7
|
User Agency (balsamy.thirunagalingam@ril.com)
|
REPLY
|
DFO (Theni)
|
06/05/2021
|
The correction have been made as per the instruction received
|
|
8
|
DFO (Theni)
|
EDS
|
User Agency (balsamy.thirunagalingam@ril.com)
|
06/05/2021
|
The User Agency is requested to report whether this proposed OFC cable will be laid along the left side or right side of towards New Bus Stand to Collector Office Road and also to confirm the depth of the trench.
|
|
9
|
User Agency (balsamy.thirunagalingam@ril.com)
|
REPLY
|
DFO (Theni)
|
07/05/2021
|
The correction have been made as per the instruction received
|
|
10
|
DFO (Theni)
|
EDS
|
User Agency (balsamy.thirunagalingam@ril.com)
|
10/05/2021
|
The User Agency is requested to report whether this proposed OFC cable will be laid along the left side or right side of towards New Bus Stand to Collector Office Road and also to confirm the depth of the trench.
|
|
11
|
User Agency (balsamy.thirunagalingam@ril.com)
|
REPLY
|
DFO (Theni)
|
15/05/2021
|
The correction have been made as per the instruction received
|
|
12
|
DFO (Theni)
|
REPLY
|
CF (Madurai)
|
02/06/2021
|
I submit that the reply for the query raised vide APCCF, Madurai Ref. 6361/2020/D1 dated 28.04.2021 is enclosed herewith.
|
|
13
|
Nodal Officer
|
EDS
|
CF (Madurai)
|
12/08/2021
|
The DFO is requested to furnish the details vide PCCF ref No.TS4/37431/2019 dt.10.08.2021.
|
|
14
|
CF (Madurai)
|
EDS
|
DFO (Theni)
|
16/08/2021
|
Further details called for as per PCCF letter enclosed
|
|
15
|
DFO (Theni)
|
REPLY
|
CF (Madurai)
|
22/09/2021
|
Sir,
The reply for the quriers raised is enclosed herewith.
|
|
16
|
CF (Madurai)
|
REPLY
|
Nodal Officer
|
30/09/2021
|
Revised Part II - rectified details
|
|