TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/TN/Others/145957/2021              (ii). Name of Project for which Forest Land is required : Diversion of Forest Land 0.251 Ha in S.V.G Puram Reserve Forest for Shri Shivashakthi Sideswara Temple              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of Forest Land 0.251 Ha in S.V.G Puram Reserve Forest for Shri Shivashakthi Sideswara Temple              (iv). State : Tamil Nadu              (v). Category of the Project : Others              (vi). Shape of forest land proposed to be diverted : Non Linear              (vii). Area of forest land proposed for diversion(in ha.): 0.251
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/TN/Others/145957/202113/10/202106/05/2022  29/11/2021   15/09/2022  26/03/2022   22/12/2022   23/01/2023 Tiruvallur :15/02/2023Chennai:
  01/08/2023 (Tiruvallur)

  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Circle (Chennai) on:16/08/2023  
Replied by DFO (Tiruvallur) on:12/10/2023  
Query raised by Circle (Chennai) on:28/11/2023  
Replied by DFO () on:  
Query raised by DFO (Tiruvallur) on:03/12/2024  
NOTE:- Proposal is pending at User Agency due to EDS raised by CF .