Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
CF (Vellore)
|
EDS
|
DFO (Vellore)
|
14/11/2023
|
Rectified the proposal hard copy triplicate not received. Remarks on site inspection report & specific recommendation has to be furnished
|
|
2
|
DFO (Vellore)
|
REPLY
|
CF (Vellore)
|
21/11/2023
|
proposal revised as per CF instructions
|
|
3
|
CF (Vellore)
|
EDS
|
DFO (Vellore)
|
05/12/2023
|
As per the field conditions for a width of 60 mts. a depth of 1.0 mts. is sufficient. The proposed depth of 1.65 mts. is too deep, which is unnecessary. The same User Agency has proposed 1.0 mt. depth for laying underground OFC cable. Hence a revised proposal may be submitted.
|
|
4
|
DFO (Vellore)
|
EDS
|
User Agency (mohan.ramalingam@stl.tech)
|
08/12/2023
|
As per the field conditions for a width of 60 mts. a depth of 1.0 mts. is sufficient. The Proposed depth of 1.65 mts. is too deep, which is unnecessary. The same User Agency has proposed 1.0 mt. depth for laying underground OFC cable. Hence a revised proposal may be submitted.
|
|
5
|
User Agency (mohan.ramalingam@stl.tech)
|
REPLY
|
DFO (Vellore)
|
11/02/2024
|
The correction have been made as per the instruction received
|
|
6
|
DFO (Vellore)
|
REPLY
|
CF (Vellore)
|
04/10/2024
|
I submit to state that, in the reference cited above, the Airtel (Telesonic Network Limited), Chennai had submitted a proposal through web portal for diversion of 0.063 ha. of Forest land in Pallikonda RF of Odugathur Range, Vellore Forest Division, for laying underground OFC cable to a length of 1.050 Km.
In reference 2, the Conservator of Forests has instructed that, based on field conditions, a trench width of 60 meters and a depth of 1.0 meter would be sufficient for this project. The initial proposal suggested a trench depth of 1.65 meters, which was deemed excessive and unnecessary. The user agency has since acknowledged this guidance and has confirmed that they will adhere to the revised trench depth of 1.0 meter as instructed.
Accordingly, we have revi
|
|
7
|
CF (Vellore)
|
EDS
|
DFO (Vellore)
|
09/10/2024
|
In the District Forest officer’s report the width of the trench is erroneously mentioned as 60 meters instead of 0.60 meter . Hence the District Forest officer is requested to submit the revised report .
|
|
8
|
DFO (Vellore)
|
REPLY
|
CF (Vellore)
|
10/10/2024
|
I submit to state that, in the reference cited above, the Airtel (Telesonic Network Limited), Chennai had submitted a proposal through web portal for diversion of 0.063 ha. of Forest land in Pallikonda RF of Odugathur Range, Vellore Forest Division, for laying underground OFC cable to a length of 1.050 Km.
In reference 2, the Conservator of Forests has instructed that, based on field conditions, a trench width of 60 meters and a depth of 1.0 meter would be sufficient for this project. The initial proposal suggested a trench depth of 1.65 meters, which was deemed excessive and unnecessary. The user agency has since acknowledged this guidance and has confirmed that they will adhere to the revised trench depth of 1.0 meter as instructed.
Accordingly, we have revi
|
|
9
|
State secretary
|
EDS
|
Nodal Officer
|
14/11/2024
|
Letter No 8793294-1, dated 14.11.2024.
|
|
10
|
Nodal Officer
|
EDS
|
CF (Vellore)
|
21/11/2024
|
The CF is requested to furnish the details called for by the Government vide PCCF ref No.TS3/10787/2022 dt.20.11.2024.
|
|
11
|
CF (Vellore)
|
EDS
|
DFO (Vellore)
|
27/11/2024
|
The DFO is requested to furnish the details called for by the Government vide PCCF ref No.TS3/10787/2022 dt.20.11.2024.
|
|
12
|
DFO (Vellore)
|
REPLY
|
CF (Vellore)
|
13/12/2024
|
I submit that the essential detail, as called for Conservator of Forest, Vellore Circle, Vellore. are furnished as below ( Letter uplodded)
|
|
13
|
CF (Vellore)
|
REPLY
|
Nodal Officer
|
18/12/2024
|
i furnish with the details called by the govt enclosed herewith
|
|
14
|
Nodal Officer
|
EDS
|
CF (Vellore)
|
20/12/2024
|
The CF is requested to furnish the details vide PCCF ref No.TS3/10787/2022 dt.20.12.2024
|
|