TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/TN/OFC/116522/2020              (ii). Name of Project for which Forest Land is required : Laying of underground OFC along Cumbam-Cumuli NH road from Lower camp to Kumuli through Suranganar RF              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Laying of underground OFC along Cumbam-Cumuli NH road from Lower camp to Kumuli through Suranganar RF in Theni District              (iv). File no. : F.No. 4-TNB115/2023-CHN              (v). State : Tamil Nadu              (vi). Category of the Project : Optical Fibre Cable              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.193
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/TN/OFC/116522/202022/12/202003/02/2021   31/08/2021   03/09/2021   25/10/2021 Theni :03/11/2021Madurai:
  07/03/2022 (Theni)

Tamil Nadu:
29/03/2022
Tamil Nadu:
13/12/2022
Chennai:
18/11/2023
07/12/2023
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by State Government (Tamil Nadu) on:11/01/2023  
Replied by Nodal Officer (Tamil Nadu) on:03/04/2023  
Query raised by State Government (Tamil Nadu) on:16/05/2023  
Replied by Nodal Officer (Tamil Nadu) on:11/08/2023  
Query raised by Nodal Officer (Tamil Nadu) on:27/05/2022  
Replied by Circle(Madurai) on:26/09/2022  
Query raised by Nodal Officer (Tamil Nadu) on:11/01/2023  
Replied by Circle(Madurai) on:14/03/2023  
Query raised by Nodal Officer (Tamil Nadu) on:16/05/2023  
Replied by Circle(Madurai) on:26/07/2023  
Query raised by Circle (Madurai) on:01/06/2022  
Replied by DFO (Theni) on:25/07/2022  
Query raised by Circle (Madurai) on:28/07/2022  
Replied by DFO (Theni) on:01/09/2022  
Query raised by Circle (Madurai) on:27/01/2023  
Replied by DFO (Theni) on:11/03/2023  
Query raised by Circle (Madurai) on:19/05/2023  
Replied by DFO (Theni) on:12/07/2023  
Query raised by DFO (Theni) on:17/11/2021  
Replied by UA on :27/11/2021  
Query raised by DFO (Theni) on:05/01/2022  
Replied by UA on :31/01/2022  
Query raised by DFO (Theni) on:16/02/2022  
Replied by UA on :17/02/2022  
Query raised by DFO (Theni) on:06/06/2022  
Replied by UA on :20/06/2022  
Query raised by DFO (Theni) on:23/02/2023  
Replied by UA on :26/02/2023  
Query raised by DFO (Theni) on:02/03/2023  
Replied by UA on :06/03/2023  
NOTE:- Stage-I Approval accorded by : Regional Office .