Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
Nodal Officer
|
EDS
|
CF (Dindigul)
|
25/05/2023
|
The CF is requested to rectify the details vide PCCF ref No.Ts4/8136/2022 dt.25.05.2023
|
|
2
|
CF (Dindigul)
|
EDS
|
DFO (Dindigul)
|
26/05/2023
|
The DFO is requested to rectify the details vide PCCF ref No.Ts4/8136/2022 dt.25.05.2023
|
|
3
|
DFO (Dindigul)
|
EDS
|
User Agency (tlsundhar990@gmail.com)
|
09/06/2023
|
submit CA land detail to be handed over to Forest Department suitable for raising Compensatory Afforestation
|
|
4
|
User Agency (tlsundhar990@gmail.com)
|
REPLY
|
DFO (Dindigul)
|
02/08/2023
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Dindigul)
|
EDS
|
User Agency (tlsundhar990@gmail.com)
|
18/08/2023
|
The User Agency is requested to upload CA land details and submit the hard copy in Dindigul Division
|
|
6
|
User Agency (tlsundhar990@gmail.com)
|
REPLY
|
DFO (Dindigul)
|
17/02/2024
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Dindigul)
|
REPLY
|
CF (Dindigul)
|
11/03/2024
|
The correction have been made as per the instruction received vide PCCF ref No.Ts4/8136/2022 dt.25.05.2023
|
|
8
|
CF (Dindigul)
|
EDS
|
DFO (Dindigul)
|
31/05/2024
|
The District Forest Officer,Dindigul is requested to upload the undertaking letter from the user agency
|
|
9
|
DFO (Dindigul)
|
EDS
|
User Agency (tlsundhar990@gmail.com)
|
31/05/2024
|
User Agency is requested to submit the undertaking for proposed Compensatory land
|
|
10
|
User Agency (tlsundhar990@gmail.com)
|
REPLY
|
DFO (Dindigul)
|
08/06/2024
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Dindigul)
|
EDS
|
User Agency (tlsundhar990@gmail.com)
|
24/07/2024
|
User Agency is requested to obtain certificate no alternate way available for reaching of patta land from the concern VAO or Revenue Officer.
|
|
12
|
User Agency (tlsundhar990@gmail.com)
|
REPLY
|
DFO (Dindigul)
|
27/07/2024
|
The correction have been made as per the instruction received
|
|
13
|
DFO (Dindigul)
|
REPLY
|
CF (Dindigul)
|
29/07/2024
|
The corrections have been made as per the instructions received from CF, Dindigul dated:31.05.2024
|
|
14
|
CF (Dindigul)
|
EDS
|
DFO (Dindigul)
|
28/08/2024
|
Diversion of 0.053 Ha of forest land for pathway to Agricultural land for SF.No.386 and 389 i K.C patty village in Kodaikanal Taluk in Kokkupari RF
|
|
15
|
DFO (Dindigul)
|
REPLY
|
CF (Dindigul)
|
25/09/2024
|
Corrections have been made as per the instructions received from PCCF Chennai &CF, Dindigul
|
|
16
|
CF (Dindigul)
|
REPLY
|
Nodal Officer
|
07/10/2024
|
The rectifications have been made as per the instructions received vide PCCF ref No.Ts4/8136/2022 dt.25.05.2023
|
|
17
|
Nodal Officer
|
EDS
|
CF (Dindigul)
|
14/11/2024
|
The EDS reply uploaded by CF has been scrutinized and short comings found. Justification shall be provided in detail. UA reported the proposal is for FC WL Clearance. It shall be clarified. District Collector certificate shall be provided with Name and Office seal. Original documents duly signed shall be scanned and uploaded. Trees to be felled shall be clarified. Correct details of CA scheme shall be uploaded. Document not relevant to this proposal shall be removed. Hence, CF and DFO are requested to rectify the above short comings.
|
|
18
|
CF (Dindigul)
|
EDS
|
DFO (Dindigul)
|
25/11/2024
|
As per the PCCF reference the Dfo,Dgl requested to rectify the above short coming and resubmit the proposal in full shape early.
|
|
19
|
DFO (Dindigul)
|
EDS
|
User Agency (tlsundhar990@gmail.com)
|
27/11/2024
|
As per the PCCF reference the User Agency is requested to rectify the short comings noted in the PCCF reference at early.
|
|
20
|
User Agency (tlsundhar990@gmail.com)
|
REPLY
|
DFO (Dindigul)
|
18/12/2024
|
The correction have been made as per the instruction received
|
|
21
|
DFO (Dindigul)
|
REPLY
|
CF (Dindigul)
|
18/12/2024
|
Corrections have been made as per the instructions received from PCCF Chennai &CF, Dindigul
|
|
22
|
CF (Dindigul)
|
REPLY
|
Nodal Officer
|
03/01/2025
|
Proposal for diversion of 0.053 ha of forest land for pathway to Agricultural land in SF.No.386 and 389 of K.C.Patti village, Kodaikanal Taluk Additional details – submission of – regarding
|
|
23
|
Nodal Officer
|
EDS
|
CF (Dindigul)
|
02/05/2025
|
The CF Dindigul and the DFO Dindigul are requested to rectify the above shortcomings and
resubmit the proposal in full shape early
|
|
24
|
CF (Dindigul)
|
EDS
|
DFO (Dindigul)
|
09/05/2025
|
The District Forest Officer, Dindigul is requested to rectify the short comings noticed by the Nodal Officer vide ref No.HOTNFD/1051/2025-TS4 Dt.02.05.2025
|
|
25
|
DFO (Dindigul)
|
EDS
|
User Agency (tlsundhar990@gmail.com)
|
27/06/2025
|
The User Agency is requested to rectify the short comings noticed by the Nodal Officer vide ref No.HOTNFD/1051/2025-TS4 Dt.02.05.2025
|
|
26
|
User Agency (tlsundhar990@gmail.com)
|
REPLY
|
DFO (Dindigul)
|
27/06/2025
|
The correction have been made as per the instruction received
|
|
27
|
DFO (Dindigul)
|
REPLY
|
CF (Dindigul)
|
01/07/2025
|
Corrections have been made as per the instructions received from PCCF Chennai &CF, Dindigul
|
|