TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/TG/WATER/19856/2016              (ii). Name of Project for which Forest Land is required : Telangana Water Grid - Segment No.15/7, Manthani, Karimnagar Dist - 7.762 Ha              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of 7.762 Ha of Forest Land in Karimnagar East Division for Laying of Water Pipeline and Construction of Structures for providing drinking water for Manthani Segment-15/7 in Karimnagar Dist in favour of Telangana Drinking Water Supply Project              (iv). File no. : 4-TSC087/2017-CHN              (v). State : Telangana              (vi). Category of the Project : Drinking Water              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 7.762
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/TG/WATER/19856/201604/06/201609/06/2016   09/06/2016   09/06/2016   13/06/2016 Karimnagar East :13/06/2016Warangal:
  30/05/2017 (Karimnagar East)

Telangana:
30/05/2017
Telangana:
30/05/2017
Hyderabad:
13/06/2017
18/07/2017
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
  
NOTE:- Stage-I Approval accorded by : Regional Office .