TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/TG/WATER/19597/2016              (ii). Name of Project for which Forest Land is required : Telangana Water Grid - Segment No.20/3, Eturunagaram, Warangal Dist - 22.258 Ha              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of 22.258 Ha of Forest Land in Warangal North Division and Warangal WLM Division for Laying of Water Pipeline and Construction of Structure of Eturunagaram Segment - 20/3 for providing drinking water to Warangal Dist in favour of TDWSP              (iv). File no. : 4-TSC048/2017-CHN              (v). State : Telangana              (vi). Category of the Project : Drinking Water              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 22.258
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/TG/WATER/19597/201623/05/201606/06/2016   07/06/2016   07/06/2016   07/06/2016

Warangal North :07/06/2016


W L M Warangal :07/06/2016

Warangal:
  19/11/2016 (Warangal North)

Warangal:
  19/11/2016 (W L M Warangal)

Telangana:
19/11/2016
Telangana:
19/11/2016
Hyderabad:
30/12/2016
13/06/2017
By :Regional Office
Telangana
23/01/2022
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Hyderabad) on:15/02/2017  
Replied by State Government(Telangana) on:13/06/2017  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by Regional Office (Hyderabad) on:17/10/2022  
Query raised by State Government (Telangana) on:29/10/2022  
Query raised by Nodal Officer on:29/10/2022  
Replied by UA on :27/08/2023  
Query raised by Nodal Officer on:07/11/2023  
Replied by UA on :  
NOTE:- Proposal is pending at User Agency due to EDS raised by RO for Stage-II .
Close(X)