TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/TG/ROAD/64751/2020              (ii). Name of Project for which Forest Land is required : Upgradation and Widening of road from Narsapur-G to Gollamada via anjani, timmapur of Narsapur-G Mandal in Nirmal District - 4.32 ha              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of 4.32 ha of forestland in Nirmal division for Upgradation and Widening of road from Narsapur-G to Gollamada via anjani, timmapur of Narsapur-G Mandal in Nirmal District in favour of PR department              (iv). State : Telangana              (v). Category of the Project : Road              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 4.32
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/TG/ROAD/64751/202026/11/202018/01/2021   28/06/2021   28/06/2021   28/06/2021 Nirmal :28/06/2021Kawal Tiger Reserve:
  28/06/2021 (Nirmal)

Telangana:
28/06/2021
Telangana:
28/06/2021
Hyderabad:
28/06/2021
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Hyderabad) on:15/07/2021  
Replied by State Government(Telangana) on:15/04/2023  
Query raised by Regional Office (Hyderabad) on:17/05/2023  
Replied by State Government(Telangana) on:03/06/2023  
Query raised by Regional Office (Hyderabad) on:09/06/2023  
Replied by State Government(Telangana) on:04/07/2023  
Query raised by Regional Office (Hyderabad) on:21/09/2023  
Replied by State Government(Telangana) on:30/09/2023  
Query raised by Regional Office (Hyderabad) on:20/11/2023  
Query raised by State Government (Telangana) on:24/09/2022  
Replied by Nodal Officer (Telangana) on:22/11/2022  
Query raised by State Government (Telangana) on:05/12/2023  
Query raised by Nodal Officer (Telangana) on:11/10/2022  
Replied by Circle(Kawal Tiger Reserve) on:21/11/2022  
Query raised by Nodal Officer (Telangana) on:26/03/2024  
Replied by Circle() on:  
Query raised by Circle (Kawal Tiger Reserve) on:11/10/2022  
Replied by DFO (Nirmal) on:21/11/2022  
Query raised by Circle (Kawal Tiger Reserve) on:12/06/2024  
Replied by DFO () on:  
NOTE:- Proposal is pending at DFO due to EDS raised by Regional Office .