| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
Regional Office
|
EDS
|
State secretary
|
29/09/2022
|
EDS
|
|
|
2
|
State secretary
|
EDS
|
Nodal Officer
|
29/10/2022
|
furnish replies on EDS as called for by the IRO
|
|
|
3
|
Nodal Officer
|
EDS
|
CF (Warangal)
|
03/03/2023
|
Furnish the EDS reply
|
|
|
4
|
CF (Warangal)
|
EDS
|
DFO (WLM Eturunagaram)
|
16/04/2023
|
DFO may Submit the replies as desired..for the EDS
|
|
|
5
|
DFO (WLM Eturunagaram)
|
EDS
|
User Agency (eerb.mulug@gmail.com)
|
08/08/2023
|
UA to furnish he information as desired by IRO
|
|
|
6
|
User Agency (eerb.mulug@gmail.com)
|
REPLY
|
DFO (WLM Eturunagaram)
|
26/09/2023
|
The correction have been made as per the instruction received
|
|
|
7
|
DFO (WLM Eturunagaram)
|
REPLY
|
CF (Warangal)
|
29/09/2023
|
Sir, EDS reply of Chityal to Bhupathipuram road details are uploaded online. along with CA and PART-II, SIR revised.
|
|
|
8
|
CF (Warangal)
|
REPLY
|
Nodal Officer
|
29/09/2023
|
Sir, EDS reply of Chityal to Bhupathipuram road details are uploaded online. along with CA and PART-II, SIR revised.
|
|
|
9
|
Nodal Officer
|
REPLY
|
State secretary
|
30/09/2023
|
EDS submitted
|
|
|
10
|
State secretary
|
REPLY
|
Regional Office
|
12/10/2023
|
Reply are furnished herewith.
|
|
|
11
|
Regional Office
|
EDS
|
State secretary
|
20/11/2023
|
EDS
|
|
|
12
|
State secretary
|
EDS
|
Nodal Officer
|
11/06/2024
|
pls submit EDS
|
|
|
13
|
Nodal Officer
|
EDS
|
CF (Warangal)
|
20/06/2024
|
PL furnished required replies
|
|
|
14
|
CF (Warangal)
|
EDS
|
DFO (WLM Eturunagaram)
|
02/11/2024
|
submit EDS replies to the UA
|
|