  (i). Proposal No. : FP/TG/ROAD/54897/2020              (ii). Name of Project for which Forest Land is required : Construction of BT Road from Chityal. to Bhupathipuram from Km 0/0 to 5/0 in Kannaigudem Manda! in Mulugu District - 1.8662 Ha              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of 1.8662 ha of forest land in WLM Eturunagaram division for Construction of BT Road from Chityal. to Bhupathipuram from Km 0/0 to 5/0 in Kannaigudem Manda! in Mulugu District in favour of Executive Engineer, Mulugu, R & B Department              (iv). State : Telangana              (v). Category of the Project : Road              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 2.613
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/TG/ROAD/54897/202011/11/202018/01/2021   20/04/2022   20/04/2022   20/04/2022 WLM Eturunagaram :20/04/2022Warangal:
  20/04/2022 (WLM Eturunagaram)

Telangana:
20/04/2022
Telangana:
20/04/2022
Hyderabad:
28/04/2022
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Hyderabad) on:29/09/2022  
Replied by State Government(Telangana) on:12/10/2023  
Query raised by Regional Office (Hyderabad) on:20/11/2023  
Query raised by State Government (Telangana) on:29/10/2022  
Replied by Nodal Officer (Telangana) on:30/09/2023  
Query raised by State Government (Telangana) on:11/06/2024  
Query raised by Nodal Officer (Telangana) on:03/03/2023  
Replied by Circle(Warangal) on:29/09/2023  
Query raised by Nodal Officer (Telangana) on:20/06/2024  
Replied by Circle() on:  
Query raised by Circle (Warangal) on:16/04/2023  
Replied by DFO (WLM Eturunagaram) on:29/09/2023  
Query raised by Circle (Warangal) on:02/11/2024  
Replied by DFO () on:  
Query raised by DFO (WLM Eturunagaram) on:08/08/2023  
Replied by UA on :26/09/2023  
NOTE:- Proposal is pending at DFO due to EDS raised by Regional Office .