| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
Regional Office
|
EDS
|
State secretary
|
27/10/2021
|
As per the attached EDS
|
|
|
2
|
State secretary
|
EDS
|
Nodal Officer
|
24/09/2022
|
pl furnish the required information as called for by the IRO
|
|
|
3
|
Nodal Officer
|
EDS
|
CF (Adilabad)
|
28/10/2022
|
furnish the required information as called for by IRO
|
|
|
4
|
CF (Adilabad)
|
EDS
|
DFO (Asifabad)
|
17/01/2023
|
Please Furnish the EDS replies
|
|
|
5
|
DFO (Asifabad)
|
REPLY
|
CF (Adilabad)
|
17/03/2023
|
Additional information for WL Mitigation plan
|
|
|
6
|
CF (Adilabad)
|
REPLY
|
Nodal Officer
|
17/10/2023
|
EDS replies submitted herewith for kind perusal.
|
|
|
7
|
Nodal Officer
|
REPLY
|
State secretary
|
18/10/2023
|
EDS submitted
|
|
|
8
|
State secretary
|
REPLY
|
Regional Office
|
20/10/2023
|
Additional information submitted to IRO, vide lr dt:10.08.2023
|
|