Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
Regional Office
|
EDS
|
State secretary
|
22/09/2021
|
As per attached EDS
|
|
2
|
State secretary
|
EDS
|
Nodal Officer
|
24/09/2022
|
furnish the information as mentioned in the IRO letter
|
|
3
|
Nodal Officer
|
EDS
|
CF (Adilabad)
|
28/10/2022
|
furnish the required information as called for by IRO
|
|
4
|
CF (Adilabad)
|
EDS
|
DFO (Kagaznagar)
|
17/01/2023
|
Please Furnish the EDS replies
|
|
5
|
DFO (Kagaznagar)
|
EDS
|
User Agency (eeprasifabad@gmail.com)
|
23/03/2023
|
Upload the Wildlife proposal and EDS raised by IRO Hyd
|
|
6
|
User Agency (eeprasifabad@gmail.com)
|
REPLY
|
DFO (Kagaznagar)
|
04/07/2023
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Kagaznagar)
|
REPLY
|
CF (Adilabad)
|
17/10/2023
|
Reply submitted to the EDS raised IRO vide F.No. 4-TSB188/2021-HYD/74, Dt: 22.09.2021.
|
|
8
|
CF (Adilabad)
|
REPLY
|
Nodal Officer
|
17/10/2023
|
NBWL approval letter is submitted herewith as EDS Reply
|
|
9
|
Nodal Officer
|
REPLY
|
State secretary
|
17/10/2023
|
NBWL approval submitted
|
|
10
|
State secretary
|
REPLY
|
Regional Office
|
20/10/2023
|
Additional information furnished to IRO vide letter dt:05.10.2023
|
|