TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/TG/ROAD/20335/2016              (ii). Name of Project for which Forest Land is required : Construction of Korutla to Mallapur Road from km 15/0 to 26/250 in Jagitial District - 7.635 Ha              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of 7.635 Ha of Forest Land in Jagitial Division for Construction of Korutla to Mallapur Road from km 15/0 to 26/250 in Karimnagar District in favour of R & B Dept, Karimnagar              (iv). File no. : 4-TSC145/2019-CHN              (v). State : Telangana              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 7.635
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/TG/ROAD/20335/201604/07/201612/03/2017  06/07/2016   15/02/2019  16/09/2016   15/02/2019   15/02/2019 Jagtiyal :15/02/2019karimnagar:
  15/02/2019 (Jagtiyal)

Telangana:
15/02/2019
Telangana:
15/02/2019
Hyderabad:
15/02/2019
07/03/2019
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
  
NOTE:- Stage-I Approval accorded by : Regional Office .