Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Kothagudem)
|
EDS
|
User Agency (ramanadham.bugga@gmail.com)
|
06/10/2016
|
Proposal is submitted for diversion of 2.4 ha, whereas as per the field verification the forest area required is 2.57 Ha. Hence, it is requested to revise the proposal for 2.57 Ha.
|
|
2
|
User Agency (ramanadham.bugga@gmail.com)
|
REPLY
|
DFO (Kothagudem)
|
06/10/2016
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Kothagudem)
|
EDS
|
User Agency (ramanadham.bugga@gmail.com)
|
04/01/2018
|
It is requested to submit RoFR Act Certificate obtained from the District Collector concerned alongwith all required enclosures for further consideration of the proposal.
|
|
4
|
User Agency (ramanadham.bugga@gmail.com)
|
REPLY
|
DFO (Kothagudem)
|
14/04/2018
|
The correction have been made as per the instruction received
|
|
5
|
Regional Office
|
EDS
|
State secretary
|
27/09/2018
|
As per the documents uploaded in the web portal, it appears that the State Govt has already been accorded approval under GA category for the project and appears to be forwarded to the RO inadvertently. May please rectify the same in consultation with NIC
|
|
6
|
State secretary
|
EDS
|
Nodal Officer
|
04/08/2023
|
for necessary action as per the quarry raised by IRO
|
|
7
|
Nodal Officer
|
REPLY
|
State secretary
|
17/10/2023
|
EDS submitted
|
|