| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
DFO (Siddipet)
|
EDS
|
User Agency (gmrrocksand@gmail.com)
|
27/12/2022
|
Upload MAP and Revised KML of the project as the area is revised
|
|
|
2
|
User Agency (gmrrocksand@gmail.com)
|
REPLY
|
DFO (Siddipet)
|
27/12/2022
|
The correction have been made as per the instruction received
|
|
|
3
|
Nodal Officer
|
EDS
|
CF (Medak)
|
06/06/2023
|
Proposal returned to UA for attending shortcoming
|
|
|
4
|
CF (Medak)
|
EDS
|
DFO (Siddipet)
|
19/07/2024
|
submit replies to the EDS raised by PCCF
|
|