| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
Regional Office
|
EDS
|
State secretary
|
30/09/2021
|
As per attached EDS
|
|
|
2
|
State secretary
|
EDS
|
Nodal Officer
|
24/09/2022
|
furnish the information as mentioned in the enclosed GOI ref
|
|
|
3
|
Nodal Officer
|
EDS
|
CF (kothagudem)
|
28/10/2022
|
furnish the required information as called for by IRO
|
|
|
4
|
CF (kothagudem)
|
EDS
|
DFO (Wl Gudur)
|
28/06/2023
|
Pls submit EDS replies urgently
|
|
|
5
|
DFO (Wl Gudur)
|
REPLY
|
CF (kothagudem)
|
17/10/2023
|
Sir, Reply to the EDS is Submitted of Mattewada to veerampet road approved by NBWL _6-123-2022WL dt: 17.07.2023
|
|
|
6
|
CF (kothagudem)
|
REPLY
|
Nodal Officer
|
17/10/2023
|
Sir, EDS reply is Submitted for Mattewada to veerampet road approved by NBWL _6-123-2022WL dt: 17.07.2023 in 73rd NBWL meeting
|
|
|
7
|
Nodal Officer
|
EDS
|
CF (kothagudem)
|
18/10/2023
|
Pls upload correct CA NFL and DFL kml file by DFO or UA
|
|
|
8
|
CF (kothagudem)
|
EDS
|
DFO (Wl Gudur)
|
19/10/2023
|
Pls upload correct CA NFL and DFL kml file by DFO or UA
|
|