TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/TG/Others/33623/2018              (ii). Name of Project for which Forest Land is required : Laying of Optical Fiber cable for 4G connectivity between Indalwai Kondur Under Nizamabad Forest division-0.1312 Ha              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Laying of Optical Fibre Cable along the road between Indalvai - Kondur within the existing RoW under Nizamabad Division for providing LTE Voice & Data Services in Telangana State.              (iv). State : Telangana              (v). Category of the Project : Others              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 0.1312
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/TG/Others/33623/201814/05/201831/05/2018   27/08/2018   27/08/2018   31/10/2018 Nizamabad :31/10/2018Nizamabad:
  31/10/2018 (Nizamabad)

Telangana:
31/10/2018
Telangana:
31/10/2018
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
  
NOTE:- Proposal is pending at State Government .