TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/TG/Others/151863/2022              (ii). Name of Project for which Forest Land is required : Construction of Permanent Helipad adjoinging Potti Sriramulu Telugu Vishwa Vidyalaym university and District Collectorate office in Nalgonda District - 1.1509 Ha              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of 1.1509 Ha of forest land in Gollaguda RF of Nalgonda Division for Construction of Permanent Helipad adjoinging Potti Sriramulu Telugu Vishwa Vidyalaym university and District Collectorate office in Nalgonda District in favor of Engineer-in-Chief (R&B) NH, Buildings & CRF ,Errumanzil, H              (iv). File no. : 4-TSB247/2022-HYD              (v). State : Telangana              (vi). Category of the Project : Others              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 1.1509
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/TG/Others/151863/202201/02/202214/02/2022   14/02/2022   14/02/2022   14/02/2022 Nalgonda :14/02/2022Amrabad-TR:
  14/02/2022 (Nalgonda)

Telangana:
14/02/2022
Telangana:
14/02/2022
Hyderabad:
14/02/2022
08/03/2022
By :Regional Office
Telangana
26/04/2022
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Hyderabad) on:21/02/2022  
Replied by State Government(Telangana) on:28/02/2022  
Query raised by State Government (Telangana) on:23/02/2022  
Replied by Nodal Officer (Telangana) on:24/02/2022  
Query raised by Nodal Officer (Telangana) on:23/02/2022  
Replied by Circle(Amrabad-TR) on:24/02/2022  
Query raised by Circle (Amrabad-TR) on:23/02/2022  
Replied by DFO (Nalgonda) on:24/02/2022  
Query raised by DFO (Nalgonda) on:23/02/2022  
Replied by UA on :23/02/2022  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by Regional Office (Hyderabad) on:24/06/2022  
Replied by State Government(Telangana) on:28/10/2022  
Query raised by Regional Office (Hyderabad) on:14/12/2022  
Replied by State Government(Telangana) on:22/09/2023  
Query raised by Regional Office (Hyderabad) on:13/11/2023  
Query raised by State Government (Telangana) on:28/10/2022  
Replied by Nodal Officer (Telangana) on:28/10/2022  
Query raised by State Government (Telangana) on:28/04/2023  
Replied by Nodal Officer (Telangana) on:01/07/2023  
Query raised by State Government (Telangana) on:09/07/2024  
Query raised by Nodal Officer on:13/11/2024  
NOTE:- Proposal is pending at User Agency due to EDS raised by RO for Stage-II .